Inspection
Summary
Permit Status of (Open) as of Report Date: 04/16/2020 9:22 am
Permit Details Permit Number: 11-00217
Bealls Commercial Remodel
125 Valley River Dr
Commercial - Remodel
Permit Issued Date: 09/24/2014
Permit Inspection Statistics
11Total Inspections Completed:
10Total Inspections Passed:
Inspection Pass Rate: 90.91%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building
06/30/2011PassPLL ADMINCommercial Framing/Structure Inspection
As per Jon BerryInspector Comments:
06/30/2011PassPLL ADMINCommercial Sheetrock/Drywall Inspection
As per Jon BerryInspector Comments:
08/11/2011FailPLL ADMINCommercial Building Final
As per Jon Berry
Fire ext required front and back
Vert grab bars req'd restrooms
Fire alarm test required
Inspector Comments:
09/12/2011PassPLL ADMINCommercial Building Final
As per Jon Berry
Brett did partial
Inspector Comments:
Electrical
06/23/2011PassBret StoddardCommercial Electrical Rough-in
Approved for cover in the framed walls only.Inspector Comments:
08/11/2011PassBret StoddardCOM, COM-A, COM-R, and COM-T Electrical Final Inspection
Approved for a final and C.O.-they labeled the panel and re-wired the RTU's back
in after the roofer took them off-from prior inspection(8/10/11).
Inspector Comments:
Fire
08/16/2011PassBret StoddardFire Alarm Final Inspection
Approved for a final-after verification of the air handlers being 1800 CFM as per
Johnny Watson-shut off power to FACP at 2:05pm 8/15, turned power back on at
2:20pm 8/16, ran the notification devices for 5 minutes and 20 seconds in the
Beall's side of the building on new power supply. Received CFM air handler specs
8/17/11.
Inspector Comments:
08/16/2011PassBret StoddardFire Department Final Inspection
Page 1 of 2
(Continued)
Permit Details Permit Number: 11-00217
Bealls Commercial Remodel
125 Valley River Dr
Commercial - Remodel
Permit Status of (Open) as of Report Date: 04/16/2020 9:22 am
Permit
Inspection
Summary
Mechanical
08/11/2011PassPLL ADMINHVAC Rough-in
As per Jon BerryInspector Comments:
08/22/2011PassPLL ADMINHVAC Final Inspection
As per Jon Berry
HVAC final completed.
Inspector Comments:
Plumbing
08/12/2011PassDon AllenPlumbing Final Inspection
its all approved for the c oInspector Comments: