HomeMy WebLinkAboutINSPECTION SUMMARY - 11-00331 - Blue Water Days Bldg #1 - 21 PlexPermit
Inspection
Summary
Permit Status of (Open) as of Report Date: 04/13/2020 1:38 pm
Permit Details Permit Number: 11-00331
Blue Water Days Bldg #1 - 21 Plex
332 S 4th W
New Multi-Family Residence
Permit Issued Date: 03/04/2014
Permit Inspection Statistics
26Total Inspections Completed:
24Total Inspections Passed:
Inspection Pass Rate: 92.31%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building
4/5 QO: Rebar supported clearances ok. Last minute fill in. Done between other
inspections with no time to verify rebar sizes with plans. Inspected with
Foundation of building #2.
Inspector Comments:
04/05/2012PassQuinton OwensFooting Inspection
7/9 JB: Bearing Footing & Heating Lines - rebar and heating lines look good.Inspector Comments:
04/17/2012PassPLL ADMINFoundation Inspection
OK to pour as per jon berry.
7/9 Floor rebar and infloor heating ok to cover
Inspector Comments:
08/24/2012PassPLL ADMINSheeting
Exterior sheeting - ext sheeting ok to cover as per jon berry.Inspector Comments:
4/1,QO: Some studs removed in bearing walls at bathrooms on the ends.Inspector Comments:
04/29/2013PassQuinton OwensFraming/Structure Inspection
4/29,QO: Replaced missing studs.
Need to finish separation under tubs. (completed 5/1)
Inspector Comments:
05/01/2013PassQuinton OwensInsulation Inspection
2/11: Mechanical Room mostly done. Finish insul. after elect. is done.
4/15,QO: Exterior wall insulation ok
4/29,QO: Finished sealing missed areas.
Inspector Comments:
4/29, QO: Mechanical room approvedInspector Comments:
5/1, QO: fire separation in tubs - fire separation ok.Inspector Comments:
5/7,QO: 3rd floor, Correction to Jon's instructions - Start double drywall on top
floor ceiling (or rate draft stop. For separation of top units.
Inspector Comments:
5/22,QO: 2nd floor - 3 units with missed screws (marked wth penciled X by front
door).
Inspector Comments:
06/11/2013PassQuinton OwensSheetrock/Drywall Inspection
6/11,QO: 2nd floor reinspect not requested (Rooms Textured) 2 unfixed spots
relocated for adding screws. 1st floor - hung and taped without inspection.
Proper drywall separation and field screws ok.
Inspector Comments:
08/29/2013FailQuinton OwensBuilding Final
Drywall patch under bathroom sink (102). ADA unit - firecaulk under bthrm sink.Inspector Comments:
Data room fire caulking and sprinkler head (units approved only)Inspector Comments:
Page 1 of 3
(Continued)
Permit Details Permit Number: 11-00331
Blue Water Days Bldg #1 - 21 Plex
332 S 4th W
New Multi-Family Residence
Permit Status of (Open) as of Report Date: 04/13/2020 1:38 pm
Permit
Inspection
Summary
11/19/2013PassQuinton OwensBuilding Final
1/27/14: Items completed and building final approved.Inspector Comments:
Electrical
08/22/2012Pass Commercial Electrical Rough-in
Wrong permit-these notes should be entered in on 11-333. Approved to insulate
the exterior walls and party walls-no SE cable is installed. Must re-inspect before
covering for SE cable and interior wiring.
Inspector Comments:
03/29/2013Pass Commercial Electrical Rough-in
Approved for cover in walls-No SER cable is installed.Inspector Comments:
05/16/2013Pass COM & MFR Electrical Service Inspection
Approved to be energized for permanent power-two meter packs.Inspector Comments:
08/30/2013Pass COM, COM-A, COM-R, and COM-T Electrical Final Inspection
Approved for a temporary final and C.O.-units only. Lights and receptacles not
done in the mehc. rooms (4), orifice size too large for flow switch, tamper
switches not installed on valves in mech. rooms (4), will re-inspect on the full
final inspection.
Inspector Comments:
09/03/2013Pass COM, COM-A, COM-R, and COM-T Electrical Final Inspection
Approved for a final and C.O.-electrical only, also inspected the fire alarm on this
inspection-Approved for a temporary only.
Inspector Comments:
10/31/2013Pass Commercial Electrical Rough-in
approved for cover on the east portion office area and mechanical room.Inspector Comments:
02/19/2014Pass COM, COM-A, COM-R, and COM-T Electrical Final Inspection
Approved for a final and C.O. entire building.Inspector Comments:
Page 2 of 3
(Continued)
Permit Details Permit Number: 11-00331
Blue Water Days Bldg #1 - 21 Plex
332 S 4th W
New Multi-Family Residence
Permit Status of (Open) as of Report Date: 04/13/2020 1:38 pm
Permit
Inspection
Summary
Fire
05/10/2012PassDale PickeringFire Sprinkler Hydro
5/10 JB: hydro checked good at 200# 2hrs.
Approved as per jon berry.
Inspector Comments:
09/27/2012PassPLL ADMINFire Sprinkler Rough-in
9/27 JB: 1:35 - 214# pressure test good - approved per jon berry.Inspector Comments:
08/30/2013Pass Fire Alarm Final Inspection
Approved for a final and C.O. for fire alarm only-inspected building #2 on the
same inspection, they are tied to the same fire alarm system for both buildings.
Inspector Comments:
09/03/2013Pass Fire Alarm Final Inspection
Approved for a temporary C.O. only, flow switch-wrong orifice size for
one/smallest head in the system, tampers not installed for both buildings-# 1 and
2.
Inspector Comments:
09/23/2013Pass Fire Sprinkler Final Inspection
8/30 DP: -remove head covers #1
- Tampers on antifreeze loop #1
- Door knobs on #1 & #2
Inspector Comments:
11/19/2013Fail Fire Alarm Final Inspection
Approved for a final and C.O. building #2 only-one ticket was written for both
bldg. #1 and #2-building #1 is missing a breaker blank in mech. room panel and
sheeting needs to be installed to cover NM-B cabling, witnessed operation of
tamper switches for new loops installed.
Inspector Comments:
Mechanical
11/19/2013PassQuinton OwensHVAC Final Inspection
8/29,QO: apartments ok. do final on appendage (mech room/laundry room)Inspector Comments:
Plumbing
08/16/2012: Looks good, per Nathan Wood.Inspector Comments:
08/20/2012PassPLL ADMINPlumbing Rough-in
08/16/2012: Looks good, per Nathan Wood.Inspector Comments:
09/03/2013Pass Plumbing Water
09/03/2013Pass Plumbing Sewer
09/03/2013Pass Plumbing Final Inspection
All good for the c/oInspector Comments:
Page 3 of 3