HomeMy WebLinkAboutDEQ APPROVAL LETTER - 19-00138 - 12th W & Hwy 33 - Rexburg West Division No. 1March 31, 2020
Mitch Neihbaur
12th West Properties
127 East Main Street
Rexburg, ID 83440
Re: City of Rexburg, Rexburg West Division I Water and Sewer System Design Review
DEQ# 20-02-33.
Dear Mr. Neihbaur,
The Department of Environmental Quality (DEQ) has reviewed the design Plans and Specifications
received on March 30, 2020. The design Plans and Specifications meet state standards and are
therefore approved.
Our approval is for the design. We will give final project approval after the project is constructed and
the as-built drawings submitted for our records. This office must review any deviations from the
approved design that might result in violations of Idaho Regulations before field installation.
Within 30 days after construction, a professional engineer registered in the State of Idaho must provide
this office with as-built plans, or a letter of certification stating that the project was installed
substantially according to the approved design.
If you have any questions regarding this letter or if we can be of further assistance, please call me at
(208) 528-2650
Sincerely,
William Teuscher PE
Water Quality Engineer
Idaho Falls Regional Office
C. Keith Davidson P.E., City of Rexburg
Husk Crowther P.E., Civilize, PLLC
900 North Skyline Drive, Suite B • Idaho Falls, ID 83402 • (208) 528-2650 Brad Little, Governor
John Tippets, Director
STATE OF IDAHO
DEPARTMENT OF ENVIRONMENTAL QUALITY