HomeMy WebLinkAboutINSPECTION SUMMARY - 11-00444 - 55 E 1st N - RemodelPermit
Inspection
Summary
Permit Status of (Open) as of Report Date: 03/10/2020 1:24 pm
Permit Details Permit Number: 11-00444
55 E 1st N - Remodel
55 E 1st N
New Single Family Residence
Permit Issued Date: 05/05/2014
Permit Inspection Statistics
15Total Inspections Completed:
8Total Inspections Passed:
Inspection Pass Rate: 53.33%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
02/21/2012PassQuinton OwensFraming/Structure Inspection
Already started work before brought to bldg. dept's attention. Need header
above bathroom door on east unit. Mostly non-bearing partitions. Need to obtain
bldg permit due to occupancy change and CUP for duplex in LDR2 zone.
Header at bathroom approved 2/21, QO
Inspector Comments:
02/21/2012FailQuinton OwensSheetrock/Drywall Inspection
Bathroom partywall approved. closet in living room missing 5/8" drywall. 1/2"
drywall on some ceilings other areas have plaster. Add 5/8" to 1/2". Need to
obtain rating on plaster.
Inspector Comments:
02/22/2012N/AQuinton OwensSheetrock/Drywall Inspection
Fire occurred in basement of home. Will wait to hear from owner on plans for
building.
Inspector Comments:
11/28/2012FailQuinton OwensSheetrock/Drywall Inspection
5/8" drywall required at party wall in closet around elec. panel. Bathroom party
wall not yet drywalled.
Inspector Comments:
06/14/2013FailQuinton OwensBuilding Final
Address #'s to be contrasting colors with wall (both). CO detector outside
bedrooms (both units). Metal plate cover over clean out on party wall (west unit).
Fire separation in crawl space/basement. Finish nailing holes in joist hangers.
CUP required for duplex (no dormitory housing allowed & driveway paved). Heat
supply in west unit bathroom?
Inspector Comments:
09/22/2014PassQuinton OwensCommercial Sheetrock/Drywall Inspection
09/22/2014PassQuinton OwensCommercial Building Final
Page 1 of 2
(Continued)
Permit Details Permit Number: 11-00444
55 E 1st N - Remodel
55 E 1st N
New Single Family Residence
Permit Status of (Open) as of Report Date: 03/10/2020 1:24 pm
Permit
Inspection
Summary
Electrical Inspection Type
11/16/2012PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
Approved for cover in the front room of the east unit where the fire was, wires
were burned and replaced for new.
Inspector Comments:
04/10/2013FailBret StoddardSFR, SFR-B, SFR-A, SFR-R, MFR, MFR-A, MFR-R Electrical Final Inspection
Dishwashers need breaker locks-hard wired, GFCI protection required in kitchens
for counter top receptacles, GFCI protection required for all bathroom
receptacles, tamper resistant receptacles required throughout both units entirely,
AFCI protection required in all bedrooms circuits, junction box cover needed in
the crawl space, switch and connector needed for the furnace in the crawl space,
8/3 wire in the crawl space needs to be terminated, open ground in the bath
GFCI's in both units, blanks needed in the panel in the front unit, breaker locks
needed for the water heaters in both units, disposal in front unit hard wired and
cord is cut off-not listed and no disconnect for unit, call for a re-inspect when
ready.
Inspector Comments:
09/03/2013PassBret StoddardSFR, SFR-B, SFR-A, SFR-R, MFR, MFR-A, MFR-R Electrical Final Inspection
Approved for a final and C.O.-both units, items from previous inspection done,
water heaters were existing.
Inspector Comments:
Mechanical Inspection Type
04/10/2013FailQuinton OwensHVAC Final Inspection
No Condensate drainage. Support furnace exhaust. No supply vent allowed to
west uinit (East side only).
Inspector Comments:
09/22/2014PassQuinton OwensHVAC Final Inspection
Plumbing Inspection Type
02/09/2012PassDon AllenPlumbing Rough-in
all good to coverInspector Comments:
05/28/2013FailDon AllenPlumbing Final Inspection
4/10/13 DA: Disposal kit need for kit. sink.
Need auto vent in 2 bath sink.
Need auto vent in kitchen
need to put t&p drops in water heater.
Inspector Comments:
09/22/2014PassDon AllenPlumbing Final Inspection
Page 2 of 2