Permit Status of (Open) as of Report Date: 02/14/2020 9:45 am
Permit Details Permit Number: 12-00403
Mesa Falls Apts Bldg #12
940 S 5th W
New Multi-Family Residence
Permit Issued Date: 07/23/2014
Permit Inspection Statistics
32Total Inspections Completed:
25Total Inspections Passed:
Inspection Pass Rate: 78.13%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
07/24/2014PassTed DyeCommercial Footing Inspection
Ufer ground on west side of building.
building number # 12
Inspector Comments:
07/25/2014PassTed DyeFoundation Inspection
07/28/2014PassTed DyeFoundation Inspection
08/01/2014PassTed DyeCommercial Footing Inspection
08/12/2014PassTed DyeCommercial Footing Inspection
09/23/2014FailTed DyeSheeting
Several partial sheets missed being totaly nailed up,plus some hold down strap
nails missed being nailed into solid wood. All places that need attention are
marked with green paint.
one stud on the top floor on the south wall and close to the east end missed
being nailed at the bottom and through the O.S.B. .
Inspector Comments:
09/25/2014PassTed DyeSheeting
10/27/2014FailTed DyeCommercial Framing/Structure Inspection
10/27/2014PassTed DyeCommercial Insulation Inspection
10/28/2014PassTed DyeCommercial Framing/Structure Inspection
10/28/2014PassTed DyeCommercial Insulation Inspection
10/29/2014FailTed DyeCommercial Insulation Inspection
1st floor insulation good
Sheetrock and Fire Caulk concealed areas through out the building.
Inspector Comments:
10/29/2014PassTed DyeCommercial Sheetrock/Drywall Inspection
10/30/2014PassTed DyeCommercial Insulation Inspection
10/31/2014PassTed DyeCommercial Sheetrock/Drywall Inspection
Bldg.12: Unit's 12201-208 are approved for tape and texture.
Also on the 1st floor, unit 12101 is also approved for tape and texture.
Inspector Comments:
Page 1 of 2
(Continued)
Permit Details Permit Number: 12-00403
Mesa Falls Apts Bldg #12
940 S 5th W
New Multi-Family Residence
Permit Status of (Open) as of Report Date: 02/14/2020 9:45 am
Permit
Inspection
Summary
02/10/2015FailTed DyeCommercial Building Final
The inspection failed due to not being able to finish landscaping because of
winter conditions.
A Temp.C.O. can be given With landscaping noted as to be finished in spring
before 1 June 15..
Inspector Comments:
02/10/2015FailTed DyeCommercial Building Final
06/12/2015PassTed DyeCommercial Building Final
Electrical Inspection Type
10/17/2014PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
11/03/2014PassBret StoddardCOM & MFR Electrical Service Inspection
02/03/2015PassBret StoddardSFR, SFR-B, SFR-A, SFR-R, MFR, MFR-A, MFR-R Electrical Final Inspection
Fire Inspection Type
10/20/2014PassDale PickeringFire Sprinkler Rough-in
Approved per Dave Davis.Inspector Comments:
01/13/2015PassDale PickeringFire Sprinkler Hydro
02/05/2015PassBret StoddardFire Alarm Final Inspection
Mechanical Inspection Type
10/21/2014FailDon AllenHVAC Rough-in
The paper needs to be removed around the water heater vents where they go
throw the roof. Need inch clearance around the water heater vents. Call for
reinspect
Inspector Comments:
10/22/2014PassDon AllenHVAC Rough-in
Good to cover the mechanical rough in.Inspector Comments:
02/11/2015PassDon AllenHVAC Final Inspection
Good for the c/oInspector Comments:
Plumbing Inspection Type
08/08/2014PassDon AllenPlumbing Underground Inspection
All good to cover the ground workInspector Comments:
10/14/2014PassDon AllenPlumbing Rough-in
rough in all good to coverInspector Comments:
11/13/2014FailDon AllenWater Meter Inspection
01/27/2015PassDon AllenPlumbing Final Inspection
07/22/2015PassDon AllenWater Meter Inspection