HomeMy WebLinkAboutINSPECTION SUMMARY - 12-00280 - South Exit Travel Center & Site PlanPermit
Inspection
Summary
Permit Status of (Open) as of Report Date: 02/06/2020 11:30 am
Permit Details Permit Number: 12-00280
South Exit Travel Center & Site Plan
944 University Blvd
New Commercial Building
Permit Issued Date: 07/29/2014
Permit Inspection Statistics
26Total Inspections Completed:
24Total Inspections Passed:
Inspection Pass Rate: 92.31%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
07/23/2012PassQuinton OwensCommercial Footing Inspection
North end with lower existing grade was dug out 12" and filled with compacted
base.
Ufer installed (Bret inspected)
Inspector Comments:
07/24/2012PassQuinton OwensFoundation Inspection
2 Bars in top, 2 in bottom, 1 in middle. Vert. rebar about 18" oc.Inspector Comments:
09/05/2012PassPLL ADMINCommercial Insulation Inspection
As per Jon BerryInspector Comments:
09/07/2012PassPLL ADMINCommercial Framing/Structure Inspection
As per Jon Berry.
sheathing nailing n and w walls ok up 1 sheet
all sheathing ok to cover
8/22/12 - Sheathing OK to cover except NE corner
8/17/12 - Nailing on bottom sheet North and west walls OK to cover only
Inspector Comments:
09/07/2012PassPLL ADMINCommercial Sheetrock/Drywall Inspection
As per Jon Berry.
Few areas need correcting Approved
Inspector Comments:
10/17/2012PassPLL ADMINSidewalk Inspection
As per Jon Berry.Inspector Comments:
10/18/2012PassPLL ADMINCommercial Building Final
As per Jon Berry.
Completed except for pumps and canopy
Inspector Comments:
Page 1 of 4
(Continued)
Permit Details Permit Number: 12-00280
South Exit Travel Center & Site Plan
944 University Blvd
New Commercial Building
Permit Status of (Open) as of Report Date: 02/06/2020 11:30 am
Permit
Inspection
Summary
Electrical Inspection Type
08/29/2012PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
Approved for cover in the interior and exterior walls only-no ceiling inspection.Inspector Comments:
10/01/2012PassBret StoddardElectrical Underground Inspection
7/23/12 - Approved for cover-ufer, copper connected to a #4 rebar in the two
locations, continuous rebar around the entire footings of the building.
10/1/12 - Walked through the underground and the entire building and electrical
service to make sure everything meets code and the plan. Approved to continue.
Inspector Comments:
10/01/2012PassBret StoddardCOM & MFR Electrical Service Inspection
Approved to be energized for permanent power.Inspector Comments:
10/10/2012PassBret StoddardCOM, COM-A, COM-R, and COM-T Electrical Final Inspection
Approved to install the ceiling tiles throughout the building-need K.O. seals
installed throughout-leave these tiles out for final inspection.
Inspector Comments:
10/18/2012FailBret StoddardCOM, COM-A, COM-R, and COM-T Electrical Final Inspection
Need to label the panels throughout the building, breakers blanks needed in all
panels, ice cream machine receptacle missing cover, breakers not correctly sized
for RTU's-ordered, drive thru signs not tied in electrically, fuel dispensers not
installed under the canopy, emergency push button for fuel dispensers not
installed, call for a re-inspect when ready.
Inspector Comments:
10/25/2012PassBret StoddardCOM, COM-A, COM-R, and COM-T Electrical Final Inspection
Approved for a final and C.O.-breakers must be labeled throughout-were taken
care of before leaving-also inspected the car wash portion of this project which is
permit #12 355, Approved for a final-as per Jane Shaw. Inspected the signs also
on this inspection for a final-(12-358)-no seperate ticket was written for the
inspection of the signs.
Inspector Comments:
Page 2 of 4
(Continued)
Permit Details Permit Number: 12-00280
South Exit Travel Center & Site Plan
944 University Blvd
New Commercial Building
Permit Status of (Open) as of Report Date: 02/06/2020 11:30 am
Permit
Inspection
Summary
Fire Inspection Type
10/01/2012PassBret StoddardFire Underground Inspection
8/2/12 - Jon Berry - Approved.
10/1/12 - Bret Stoddard - Inspected the fuel dispensers as a part of a fire
inspection and noticed the vent lines for the fuel tanks were going up the sign in
front of the building requiring the sign to now be a hazardous location in
accordance with the NEC, so after some discussion with the general contractor
and the fuel dispensing contractor, they are moving the vent lines to above the
canopy instead. Approved to move forward with the project.
Inspector Comments:
10/10/2012PassDale PickeringFire Sprinkler Hydro
8/2/12 - Jon Berry - Underground riser hydro test (tested good at 200 #)
10/10/12 - Approved as witnessed, main flush-10 minutes, to riser flushed-5
minutes, 205 PSI hydrostatic test began at 1:15PM and finished at 3:15PM still at
205 PSI then released the pressure, see 3-D's inspection report that will be
submitted upon completion of project.
Inspector Comments:
10/17/2012PassPLL ADMINFire Department Final Inspection
As per Jon Berry. Need 2A20BC Fire extinguisher w/in 75' of pumps and fill ports.Inspector Comments:
10/18/2012PassBret StoddardFire Sprinkler Final Inspection
Approved and witnessed flow test, main drain, and tampers are functional-as
built drawings for fire sprinkler system still needed and testing reports
also-before issuing C.O.
Inspector Comments:
10/19/2012PassBret StoddardFire Alarm Final Inspection
Approved/witnessed fire alarm final-A/C power loss at 3:08PM 10/18/12, 5
minute test at
3:10PM 10/19/12, restored alarm system back to normal at 3:40PM 10/19/12,
still need to receive the print out that the alarm system notified the alarming
station.
Inspector Comments:
Mechanical Inspection Type
09/07/2012PassPLL ADMINHVAC Rough-in
As per Jon Berry. Int ducting OKInspector Comments:
10/17/2012PassPLL ADMINHVAC Final Inspection
As per Jon Berry.
Ducting in ceiling ok to cover.
10/12 ANSUL system checked good on both hoods.
Inspector Comments:
Page 3 of 4
(Continued)
Permit Details Permit Number: 12-00280
South Exit Travel Center & Site Plan
944 University Blvd
New Commercial Building
Permit Status of (Open) as of Report Date: 02/06/2020 11:30 am
Permit
Inspection
Summary
Plumbing Inspection Type
08/03/2012PassDon AllenPlumbing Underground Inspection
All good to cover the ground work.Inspector Comments:
08/21/2012FailDon AllenPlumbing Rough-in
Need to change vent in the downstairs kitchenInspector Comments:
08/31/2012PassDon AllenPlumbing Rough-in
All good to cover.Inspector Comments:
09/05/2012PassDon AllenPlumbing Sewer
09/05/2012PassDon AllenPlumbing Water
10/19/2012PassDon AllenPlumbing Final Inspection
Page 4 of 4