HomeMy WebLinkAboutCOMCHECK - 20-00038 - Rudd & Company - New CommercialCOMcheck Software Version COMcheckWeb
Envelope Compliance Certificate
Project Title:
2015 IECC
Project Type:New Construction
Permit No.2020-0038
Vertical Glazing / Wall Area:18%
Location:Rexburg, Idaho
Climate Zone:6b
Construction Site:
490 First American Circle
Rexburg, Idaho 83440
Owner/Agent:
Jay Rice
Advantage Architecture PC
81 Highway 31
Swan Valley, Idaho 83449
208-317-7423
jay@advantage-arch.com
Designer/Contractor:
Hayley Jones
Project Information
Energy Code:
Reduced interior lighting power. Requirements are implicitly enforced within interior lighting allowance calculations.
Additional Efficiency Package(s)
Building Area Floor Area
1-Office : Nonresidential 8145
Envelope Assemblies
Assembly Cavity
R-Value
Cont.
R-Value
Proposed
U-Factor
Budget U-
Factor(a)
Gross Area
or
Perimeter
Roof: Insulation Entirely Above Deck, [Bldg. Use 1 - Office]8145 ---38.0 0.026 0.032
Ext. Wall: Wood-Framed, 24in. o.c., [Bldg. Use 1 - Office]5838 21.0 8.0 0.038 0.051
Window: Metal Frame with Thermal Break: Fixed, Perf. Specs.:
Product ID H1635, SHGC 0.30, [Bldg. Use 1 - Office] (b)
992 ------0.300 0.360
Door: , Perf. Specs.: Product ID H1635, SHGC 0.30, [Bldg. Use 1
- Office] (b)
72 ------0.300 0.770
Floor: Unheated Slab-On-Grade, Vertical 4 ft., [Bldg. Use 1 -
Office] (c)
417 ---8.0 0.504 0.540
(a)Budget U-factors are used for software baseline calculations ONLY, and are not code requirements.
(b)Fenestration product performance must be certified in accordance with NFRC and requires supporting documentation.
(c)Slab-On-Grade proposed and budget U-factors shown in table are F-factors.
Envelope Compliance Statement
Compliance Statement: The proposed envelope design represented in this document is consistent with the building plans,
specifications, and other calculations submitted with this permit application. The proposed envelope systems have been
designed to meet the 2015 IECC requirements in COMcheck Version COMcheckWeb and to comply with any applicable
mandatory requirements listed in the Inspection Checklist.
Envelope PASSES: Design 19% better than code
Project Title:
Data filename:
01/27/20Report date:
111 ofPage
Name - Title Signature Date
Project Title:
Data filename:
01/27/20Report date:
112 ofPage
COMcheck Software Version COMcheckWeb
Interior Lighting Compliance Certificate
Project Title:
2015 IECC
Project Type:New Construction
Permit No.2020-0038
Construction Site:
490 First American Circle
Rexburg, Idaho 83440
Owner/Agent:
Jay Rice
Advantage Architecture PC
81 Highway 31
Swan Valley, Idaho 83449
208-317-7423
jay@advantage-arch.com
Designer/Contractor:
Hayley Jones
Project Information
Energy Code:
Reduced interior lighting power. Requirements are implicitly enforced within interior lighting allowance calculations.
Additional Efficiency Package(s)
Allowed Interior Lighting Power
Proposed Interior Lighting Power
Interior Lighting TBD: No lighting fixtures specified
Project Title:
Data filename:
01/27/20Report date:
113 ofPage
COMcheck Software Version COMcheckWeb
Exterior Lighting Compliance Certificate
Project Title:
2015 IECC
Project Type:New Construction
Permit No.2020-0038
Construction Site:
490 First American Circle
Rexburg, Idaho 83440
Owner/Agent:
Jay Rice
Advantage Architecture PC
81 Highway 31
Swan Valley, Idaho 83449
208-317-7423
jay@advantage-arch.com
Designer/Contractor:
Hayley Jones
Project Information
Energy Code:
0 (Unspecified)Exterior Lighting Zone
Allowed Exterior Lighting Power
A
Area/Surface Category
B
Quantity
C
Allowed
Watts /
D
Tradable
Wattage
E
Allowed Watts
(B X C)
Total Tradable Watts (a) =
Total Allowed Watts =
Total Allowed Supplemental Watts (b) =
0
0
500
(a)Wattage tradeoffs are only allowed between tradable areas/surfaces.
(b)A supplemental allowance equal to 500 watts may be applied toward compliance of both non-tradable and tradable
areas/surfaces.
Proposed Exterior Lighting Power
Exterior Lighting TBD: Exterior lighting zone not specified (see project screen)
Project Title:
Data filename:
01/27/20Report date:
114 ofPage
COMcheck Software Version COMcheckWeb
Mechanical Compliance Certificate
Project Title:
2015 IECC
Project Type:New Construction
Permit No.2020-0038
Location:Rexburg, Idaho
Climate Zone:6b
Construction Site:
490 First American Circle
Rexburg, Idaho 83440
Owner/Agent:
Jay Rice
Advantage Architecture PC
81 Highway 31
Swan Valley, Idaho 83449
208-317-7423
jay@advantage-arch.com
Designer/Contractor:
Hayley Jones
Project Information
Energy Code:
Reduced interior lighting power. Requirements are implicitly enforced within interior lighting allowance calculations.
Additional Efficiency Package(s)
Mechanical Systems List
Quantity System Type & Description
Mechanical Compliance Statement
Compliance Statement: The proposed mechanical design represented in this document is consistent with the building plans,
specifications, and other calculations submitted with this permit application. The proposed mechanical systems have been
designed to meet the 2015 IECC requirements in COMcheck Version COMcheckWeb and to comply with any applicable
mandatory requirements listed in the Inspection Checklist.
Name - Title Signature Date
Project Title:
Data filename:
01/27/20Report date:
115 ofPage
Inspection Checklist
Requirements: 0.0% were addressed directly in the COMcheck software
COMcheck Software Version COMcheckWeb
Text in the "Comments/Assumptions" column is provided by the user in the COMcheck Requirements screen. For each
requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception
is being claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Energy Code: 2015 IECC
Section
#
& Req.ID
Plan Review Complies?Comments/Assumptions
C103.2
[PR1]1
Plans and/or specifications provide all
information with which compliance
can be determined for the building
envelope and document where
exceptions to the standard are
claimed.
Complies
Does Not
Not Observable
Not Applicable
C402.4.1
[PR10]1
The vertical fenestration area <= 30
percent of the gross above-grade wall
area.
Complies
Does Not
Not Observable
Not Applicable
C402.4.1
[PR11]1
The skylight area <= 3 percent of the
gross roof area.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
01/27/20Report date:
116 ofPage
Section
#
& Req.ID
Footing / Foundation Inspection Complies?Comments/Assumptions
C303.2
[FO4]2
Slab edge insulation installed per
manufacturer’s instructions.
Complies
Does Not
Not Observable
Not Applicable
C303.2.1
[FO6]1
Exterior insulation protected against
damage, sunlight, moisture, wind,
landscaping and equipment
maintenance activities.
Complies
Does Not
Not Observable
Not Applicable
C104
[FO3]2
Installed slab-on-grade insulation type
and R-value consistent with insulation
specifications reported in plans and
COMcheck reports.
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies table for values.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
01/27/20Report date:
117 ofPage
Section
#
& Req.ID
Framing / Rough-In Inspection Complies?Comments/Assumptions
C303.1.3
[FR12]2
Fenestration products rated in
accordance with NFRC.
Complies
Does Not
Not Observable
Not Applicable
C303.1.3
[FR13]1
Fenestration products are certified as
to performance labels or certificates
provided.
Complies
Does Not
Not Observable
Not Applicable
C402.4.3
[FR10]1
Vertical fenestration SHGC value.Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies table for values.
C402.4.3,
C402.4.3.
4
[FR8]1
Vertical fenestration U-Factor.Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies table for values.
C402.4.4
[FR14]2
U-factor of opaque doors associated
with the building thermal envelope
meets requirements.
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies table for values.
C402.5.1.
2.1
[FR19]1
The building envelope contains a
continuous air barrier that is sealed in
an approved manner and material
permeability <= 0.004 dfm/ft2. Air
barrier penetrations are sealed in an
approved manner.
Complies
Does Not
Not Observable
Not Applicable
C402.5.2,
C402.5.4
[FR18]3
Factory-built fenestration and doors
are labeled as meeting air leakage
requirements.
Complies
Does Not
Not Observable
Not Applicable
C402.5.7
[FR17]3
Vestibules are installed on all building
entrances. Doors have self-closing
devices.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
01/27/20Report date:
118 ofPage
Section
#
& Req.ID
Mechanical Rough-In Inspection Complies?Comments/Assumptions
C402.5.5,
C403.2.4.
3
[ME3]3
Stair and elevator shaft vents have
motorized dampers that automatically
close.
Complies
Does Not
Not Observable
Not Applicable
C402.5.5,
C403.2.4.
3
[ME58]3
Outdoor air and exhaust systems have
motorized dampers that automatically
shut when not in use and meet
maximum leakage rates. Check
gravity dampers where allowed.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
01/27/20Report date:
119 ofPage
Section
#
& Req.ID
Insulation Inspection Complies?Comments/Assumptions
C303.1
[IN3]1
Roof insulation installed per
manufacturer’s instructions. Blown or
poured loose-fill insulation is installed
only where the roof slope is <=3 in
12.
Complies
Does Not
Not Observable
Not Applicable
C303.1
[IN10]2
Building envelope insulation is labeled
with R-value or insulation certificate
providing R-value and other relevant
data.
Complies
Does Not
Not Observable
Not Applicable
C303.2
[IN7]1
Above-grade wall insulation installed
per manufacturer’s instructions.
Complies
Does Not
Not Observable
Not Applicable
C303.2.1
[IN14]2
Exterior insulation is protected from
damage with a protective material.
Verification for exposed foundation
insulation may need to occur during
Foundation Inspection.
Complies
Does Not
Not Observable
Not Applicable
C402.2.1
[IN17]3
Insulation intended to meet the roof
insulation requirements cannot be
installed on top of a suspended
ceiling. Mark this requirement
compliant if insulation is installed
accordingly.
Complies
Does Not
Not Observable
Not Applicable
C104
[IN6]1
Installed above-grade wall insulation
type and R-value consistent with
insulation specifications reported in
plans and COMcheck reports.
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies table for values.
C104
[IN8]2
Installed floor insulation type and R-
value consistent with insulation
specifications reported in plans and
COMcheck reports.
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies table for values.
C402.2.6
[IN18]3
Radiant panels and associated
components, designed for heat
transfer from the panel surfaces to the
occupants or indoor space are
insulated with a minimum of R-3.5.
Complies
Does Not
Not Observable
Not Applicable
C104
[IN2]1
Installed roof insulation type and R-
value consistent with insulation
specifications reported in plans and
COMcheck reports. For some ceiling
systems, verification may need to
occur during Framing Inspection.
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies table for values.
C402.5.1.
1
[IN1]1
All sources of air leakage in the
building thermal envelope are sealed,
caulked, gasketed, weather stripped
or wrapped with moisture vapor-
permeable wrapping material to
minimize air leakage.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
01/27/20Report date:
1110 ofPage
Section
#
& Req.ID
Final Inspection Complies?Comments/Assumptions
C402.5.3
[FI51]3
Where open combustion air ducts
provide combustion air to open
combustion fuel burning appliances,
the appliances and combustion air
opening are located outside the
building thermal envelope or enclosed
in a room, isolated from inside the
thermal envelope. Such rooms are
sealed and insulated.
Complies
Does Not
Not Observable
Not Applicable
C402.5.6
[FI37]1
Weatherseals installed on all loading
dock cargo doors.
Complies
Does Not
Not Observable
Not Applicable
C402.5.8
[FI26]3
Recessed luminaires in thermal
envelope to limit infiltration and be IC
rated and labeled. Seal between
interior finish and luminaire housing.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
01/27/20Report date:
1111 ofPage