HomeMy WebLinkAboutINSPECTION SUMMARY - 12-00159 - Burton Elementary Addition & Site PlanPermit
Inspection
Summary
Permit Status of (Open) as of Report Date: 01/14/2020 1:40 pm
Permit Details Permit Number: 12-00159
Burton Elementary Addition & Site Plan
2211 W 1000 S
Commercial - Addition
Permit Issued Date: 07/16/2014
Permit Inspection Statistics
17Total Inspections Completed:
17Total Inspections Passed:
Inspection Pass Rate: 100.00%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
06/01/2012PassPLL ADMINFooting Inspection
As per Jon Berry. Footings and rebar look good.Inspector Comments:
06/04/2012PassPLL ADMINFoundation Inspection
As per Jon Berry.
6/4/12 - Foundation and rebar look good.
6/12/12 - Floor footings and rebar look good.
Inspector Comments:
08/17/2012PassPLL ADMINSidewalk Inspection
As per Jon Berry. Curb & gutter has 2 rebar unsupported & not tied to existing
curb. Instructed contractor to pull rebar up off ground. Has about 4" gravel base.
(7-23, Quinton)
Inspector Comments:
08/17/2012PassPLL ADMINBuilding Final
As per Jon Berry. Final completedInspector Comments:
08/20/2012PassPLL ADMINFraming/Structure Inspection
As per Jon Berry.
7/9 N. 3/4's of roof ok to cover nailing approved CW
7/17 Sheathing and ext. wall framing passed. Needs hold downs at doorway.
Inspector Comments:
08/20/2012PassPLL ADMINInsulation Inspection
As per Jon Berry.
7/12 Roof insulation ok to cover.
Inspector Comments:
08/20/2012PassPLL ADMINSheetrock/Drywall Inspection
As Per Jon Berry.Inspector Comments:
Page 1 of 2
(Continued)
Permit Details Permit Number: 12-00159
Burton Elementary Addition & Site Plan
2211 W 1000 S
Commercial - Addition
Permit Status of (Open) as of Report Date: 01/14/2020 1:40 pm
Permit
Inspection
Summary
Electrical Inspection Type
07/17/2012PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
210 PSI-9:10AM, 210 PSI-11:10AM-hydrostatic test witnessed, visual walk
through OK, need to inspect the tie in and the sprinkler head that is moving a
few feet by the transition from existing to new, test report from the sprinkler
contractor is coming for the final.
Inspector Comments:
07/26/2012PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
7/19/12 - Approved for cover in the entryway at the end of the new wing only.Inspector Comments:
08/17/2012PassBret StoddardCOM, COM-A, COM-R, and COM-T Electrical Final Inspection
AM inspection-need dryer receptacle with four wire instead of 3 wire, blank cover
needed in room A115, connectors required for termination in door openers-ADA.
PM re-inspection, Approved for a final and C.O.-addition.
Inspector Comments:
Fire Inspection Type
08/10/2012PassDale PickeringFire Sprinkler Hydro
210 PSI-9:10AM, 210 PSI-11:10AM-hydrostatic test witnessed, visual walk
through OK, need to inspect the tie in and the sprinkler head that is moving a
few feet by the transition from existing to new, test report from the sprinkler
contractor is coming for the final.
Inspector Comments:
08/20/2012PassPLL ADMINFire Department Final Inspection
As per Jon Berry. Paperwork required to be turned inInspector Comments:
Mechanical Inspection Type
08/15/2012PassPLL ADMINHVAC Final Inspection
As per Jon Berry. HVAC final looks good.Inspector Comments:
Plumbing Inspection Type
07/30/2012PassDon AllenPlumbing Sewer
07/30/2012PassDon AllenPlumbing Water
07/30/2012PassDon AllenPlumbing Rough-in
All good to coverInspector Comments:
08/20/2012PassSAUREY AMANDAPlumbing Final Inspection
08/15/2012: Need continuous waste on 2 sinks and 1 aerator on another sink,
the contractor stated he would put them on when they show up. Looks good,
per Nathan Wood.
Inspector Comments:
Page 2 of 2