Permit Status of (Open) as of Report Date: 12/10/2019 11:28 am
Permit Details Permit Number: 12-00007
160 W 2 S - Namaste Salon Tenant Finish
160 W 2 S
Commercial Tenant Finish
Permit Issued Date: 07/03/2014
Permit Inspection Statistics
15Total Inspections Completed:
14Total Inspections Passed:
Inspection Pass Rate: 93.33%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
03/27/2012PassPLL ADMINFraming/Structure Inspection
As Per Jon BerryInspector Comments:
03/27/2012PassPLL ADMINSheetrock/Drywall Inspection
As Per Jon BerryInspector Comments:
04/20/2012PassPLL ADMINBuilding Final
As Per Jon Berry Install Fire Ext. by entry door. Temp C/OInspector Comments:
Electrical Inspection Type
03/07/2012PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
Approved for cover throughout the remodeled space.Inspector Comments:
03/13/2012PassBret StoddardCOM & MFR Electrical Service Inspection
Approved to energize the feeder from the meter main to the panel in the
occupant space (salon).
Inspector Comments:
04/18/2012PassBret StoddardCOM, COM-A, COM-R, and COM-T Electrical Final Inspection
Approved for a final and C.O.-electrician on site-made corrections, labeled all
breakers in panel-as per Jane Shaw.
Inspector Comments:
Fire Inspection Type
04/17/2012PassPLL ADMINFire Alarm Final Inspection
As Per Jon Berry-No pulls in unit Alarm/strobes tested goodInspector Comments:
04/17/2012PassPLL ADMINFire Sprinkler Final Inspection
As Per Jon BerryInspector Comments:
04/20/2012PassPLL ADMINFire Department Final Inspection
Page 1 of 2
(Continued)
Permit Details Permit Number: 12-00007
160 W 2 S - Namaste Salon Tenant Finish
160 W 2 S
Commercial Tenant Finish
Permit Status of (Open) as of Report Date: 12/10/2019 11:28 am
Permit
Inspection
Summary
Mechanical Inspection Type
03/06/2012FailPLL ADMINHVAC Rough-in
As Per Jon Berry
Jon Berry- 3/6/12-Seal ducting between duct and units (2)
Inspector Comments:
04/18/2012PassBret StoddardHVAC Final Inspection
Approved for a final and C.O.-electrician on site-made corrections, labeled all
breakers in panel-as per Jane Shaw.
Inspector Comments:
05/04/2012PassPLL ADMINHVAC Rough-in
As Per Jon BerryInspector Comments:
Plumbing Inspection Type
03/07/2012PassDon AllenPlumbing Rough-in
05/01/2012PassDon AllenPlumbing Sewer
Also Approved Water on 5/1/12 As Per Don AllenInspector Comments:
05/01/2012PassDon AllenPlumbing Final Inspection