HomeMy WebLinkAboutINSPECTION SUMMARY - 13-00179 - 60 S 5th W - Kennedy Elementary Addition & RemodelPermit
Inspection
Summary
Permit Status of (Open) as of Report Date: 11/26/2019 4:58 pm
Permit Details Permit Number: 13-00179
Kennedy Elementary Addition & Remodel
60 S 5th W
Commercial - Addition
Permit Issued Date: 07/02/2013
Permit Inspection Statistics
32Total Inspections Completed:
24Total Inspections Passed:
Inspection Pass Rate: 75.00%
Permit Inspection History *Refer to Individual Inspection Report for more Details
05/23/2013PassQuinton OwensFooting Inspection
06/03/2013PassBret StoddardElectrical Underground Inspection
5/24,QO: Partial Foundation (South,West, & NW corner)rebar per plans.Inspector Comments:
5/29,QO: Remaining Foundation. Rebar per plans. Some bars do not have
clearance; Forsgren on site to confirm correction.
Inspector Comments:
06/11/2013PassQuinton OwensFoundation Inspection
6/11,QO: Interior footings/Slab. Rebar per plans. OK to pour.Inspector Comments:
07/19/2013PassDon AllenPlumbing Underground Inspection
07/23/2013PassBret StoddardElectrical Rough-in
08/08/2013PassJoel GrayPlumbing Water
08/12/2013PassTed DyeFraming/Structure Inspection
7/15,QO: Sheathing in hallway for masonry backing. OK to cover.Inspector Comments:
08/12/2013PassTed DyeSheeting
08/23/2013PassBret StoddardElectrical Rough-in
Approved for cover-ceilings in the hallway and classrooms. J-box missing cover in
the SW room-installing before left, inspected the electrical service on this
inspection also(already energized).
Inspector Comments:
08/23/2013PassBret StoddardElectrical Service Inspection
Approved to remain energized for permanent power, inspected the electrical
service on the ceiling inspection.
Inspector Comments:
09/10/2013PassQuinton OwensHVAC Rough-in
No request for rough mechanical inspection above ceilings. Approved based on
that area being in the thermal envelope (no insulation required) and most duct is
in the attic area.
Inspector Comments:
09/11/2013PassBret StoddardElectrical Final Inspection
Gym area not ready, several open junction boxes, panels not accessible to verify
labeling, unable to verify GFCI protection on drinking fountains as water was not
on, call for a re-inspect when ready.
Inspector Comments:
09/11/2013PassDon AllenPlumbing Rough-in
Page 1 of 3
(Continued)
Permit Details Permit Number: 13-00179
Kennedy Elementary Addition & Remodel
60 S 5th W
Commercial - Addition
Permit Status of (Open) as of Report Date: 11/26/2019 4:58 pm
Permit
Inspection
Summary
09/13/2013PassBret StoddardElectrical Final Inspection
Approved for a temporary final for the classrooms only, the gym and upper level
not done, inspected the fire alarm on this inspection (9/12 & 9/13)-witnessed the
fire alarm signalling and initiating devices in the classrooms and hallways only, no
24 hour/ 5 minute test done, flow switch not tied into gong, not approved for a
final-fire alarm system. Call for a re-inspect when ready.
Inspector Comments:
10/17/2013FailBret StoddardElectrical Final Inspection
Electrical junction boxes need covers and switches not done throughout the
entire upstairs area and gym area.
Inspector Comments:
10/17/2013FailBret StoddardFire Alarm Final Inspection
Final fire alarm report not done yet, map of zones not done from fire alarm
contractor for new portion-addition, horn strobe not mounted in the mechanical
room upstairs, inspected the fire alarm on the final electrical inspection. 24
hour/5 minute test witnessed at 4:00PM 10/16-as per Troy with Omni shut off
A/C power, 4:10PM 10/17 tested and restored A/C, witnessed operation of 2 duct
detectors, 3 manual pull stations in gym area, and 2 tamper switches on the fire
riser, also horn strobe operation upstairs and in gym area.
Inspector Comments:
10/18/2013FailQuinton OwensBuilding Final
10/18: Handrails required at Accessible ramp (8% slope max). Where is tag for
gas regulator? Regulator installed sideways without venting. Handrail
non-compliant on North side of stairs (extension). 4 vents through roof not
properly sealed (silicone instead of roofing membrane)
Inspector Comments:
10/18/2013FailQuinton OwensHVAC Final Inspection
10/18: Tag missing on gas regulator installed sideways.Inspector Comments:
10/18/2013FailDale PickeringFire Sprinkler Final Inspection
Seismic bracing missing in gymInspector Comments:
10/18/2013FailDale PickeringFire Department Final Inspection
Storz required, Hydrant facing fie lane, service fire extinguishers, knox boxes
missing, Riser Room signage
Inspector Comments:
10/24/2013PassBret StoddardFire Alarm Final Inspection
Approved for a final and C.O.-zone map in main fire alarm panel, report in file
from fire alarm contractor, horn added in mechanical room upstairs, inspected
the electrical on this inspection also.
Inspector Comments:
10/24/2013PassBret StoddardElectrical Final Inspection
Approved for a final and C.O.-addition-inspected the fire alarm on this inspection
also.
Inspector Comments:
11/04/2013PassDale PickeringFire Department Final Inspection
11/04/2013PassDale PickeringFire Sprinkler Final Inspection
Page 2 of 3
(Continued)
Permit Details Permit Number: 13-00179
Kennedy Elementary Addition & Remodel
60 S 5th W
Commercial - Addition
Permit Status of (Open) as of Report Date: 11/26/2019 4:58 pm
Permit
Inspection
Summary
11/20/2013PassSAUREY AMANDAInsulation Inspection
No Insulation inspection was requested. We requested an insulation certificate
from Barry Hayes Construction. They provided the certificate and approved the
values.
Inspector Comments:
11/20/2013PassTed DyeSheetrock/Drywall Inspection
7-26 Drywall 2nd floor hallway ceiling OK
Rm A113 drywall OK to tape
7-29 Southwest class room ready for tape
South entry ready for tape
7-30 South middle drywall approved for tape
East class room approved for tape
Inspector Comments:
08/25/2014PassDon AllenPlumbing Final Inspection
All good for c/oInspector Comments:
Building Inspection Type
08/25/2014FailQuinton OwensCommercial Building Final
mechanical area not having access to public (likely only to be a few individuals at
most for occasional maintenance), handrail on North is approved without
extension with South handrail meeting required length.
temporary paper bathroom signs not yet replaced. all other previous items are
completed.
Inspector Comments:
08/26/2014PassQuinton OwensCommercial Building Final
08/26/2014PassQuinton OwensSidewalk Inspection
Sidewalks for discharge are completed. Handrail installed at ADA ramp at East
entrance to addition.
Inspector Comments:
Mechanical Inspection Type
09/10/2013FailQuinton OwensCommercial Building Final
9/10: Ductwork only (classroom). Mechanical level Ductwork approved. Duct
work above main level ceiling covered & could not inspect. Exhaust air from
Restrooms goes through heat exchanger but is also connected to other return air
duct (must exhaust outside). Remainder of mechanical level to be completed.
Inspector Comments:
08/25/2014PassQuinton OwensHVAC Final Inspection
gas pressure regulator is allowed in any position without venting to outside. heat
exchanger pulling air from bathrooms and gym approved. mechanical final
approved.
Inspector Comments:
Page 3 of 3