HomeMy WebLinkAboutRESCHECK - M19-00141 - McBride - 990 River Run - New SFRGenerated by REScheck-Web Software
Compliance Certificate
Project Landon & Kim McBride
Energy Code:
2009 IECC
Location:
Madison County, Idaho
Construction Type:
Single-family
Project Type:
New Construction
Conditioned Floor Area:
4,018 ft2
Glazing Area
19%
Climate Zone:
6 (8999 HDD)
Permit Date:
Permit Number:
Construction Site:
Owner/Agent:
Designer/Contractor:
990 River Run
Josh & Marcy Garner
Justin Stevens
Sugar City, ID 83448
330 Oaktrail Drive
Stevens Homes
Rexburg, ID 83440
PO Box 2759
Idaho Falls, ID 83403
justin@stevenshomes.com
Compliance:trade-off
Compliance: 13.8% Better Than Code Maximum UA: 536 Your UA: 462
The % Better or worse Than Code Index reflects how close to compliance the house is based on code trade-off rules.
It DOES NOT provide an estimate of energy use or cost relative to a minimum -code home.
Envelope Assemblies
t_emng: rlat (-ening or 5clssor Truss 4,018 0.0 50.0 0.019 76
Wall: Wood Frame, 16" o.c. 2,350 19.0 0.0 0.060 110
Doors Main Floor: Glass Door (over 50% glazing) 82 0.350 29
Windows Main Floor: Vinyl Frame 432 0.280 121
Wall Second Floor: Wood Frame, 16" D.C. 1,020 19.0 0.0 0.060 54
Window: Vinyl Frame 120 0.280 34
Crawl: Solid Concrete or Masonry 1,112 0.0 19.0 0.046 38
Wall height: 4.0'
Depth below grade: 3.0'
Insulation depth: 4.0'
Compliance Statement: The proposed building design described here is consistent with the building plans, specifications, and other
calculations submitted with the permit application. The proposed building has been designed to meet the 2009 IECC requirements in
REScheck Version : REScheck-Web and to comply with the r9andk'Ory req Irements list din "'REScheck Inspection Checklist.
r✓ffs� rI > f �l/t'iCS ;��-PSS �4 7� �/
Name - Title Slgg3tLo Date
Project Title: Landon & Kim McBride Report date: 10/21/19
Data filename: Page 1 of 7
r4REScheck Software Version : REScheck-Web
Inspection Checklist
Energy Code: 2009 IECC
Requirements: 0.0% were addressed directly in the REScheck software
Text in the "Comments/Assumptions" column is provided by the user in the REScheck Requirements screen. For each
requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception
is being claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Section
#
& Req.ID
Pre-Inspection/Plan Review
Plans Verified
Value
Field Verified
Value
Complies?
Comments/Assum tions
p
103.2
Construction drawings and
❑Complies
[PR111
documentation demonstrate
❑Does Not
g,
energy code compliance for the
building envelope.
❑Not Observable
❑Not Applicable
103.2,
Construction drawings and
❑Complies
403.7
documentation demonstrate
[]Does Not
[PR3]1
energy code compliance for
lighting and mechanical systems.
❑Not Observable
Systems serving multiple
❑Not Applicable
dwelling units must demonstrate
compliance with the commercial
code.
403.6
Heating and cooling equipment is
Heating:
Heating:
❑Complies
[PR2]2
sized per ACCA Manual S based
Btu/hr
Btu/hr
❑Does Not
on loads per ACCA Manual J or
other approved methods.
Cooling:
g:
Cooling:
g:
❑ Not Observable
Btu /hr
Btu/hrlin
❑Not Applicable
Additional Comments/Assumptions:
E1 JHigh Impact (Tier 1) 2 1 Medium Impact (Tier 2) 3 Low Impact (Tier 3)
Project Title: Landon & Kim McBride Report date: 10/21/19
Data filename: Page 2 of 7
F+uumionat Lomments/Assumptions:
11 High Impact (Tier 1) 2 MediumImpact (Tier 2) 3 Low Impact (Tier 3)
Project Title: Landon & Kim McBride Report date: 10/21/19
Data filename:
Page 3 of 7
ESection
#
ea.ID
Foundation Inspection
Plans Verified
Value
Field Verified
Value
Complies?
Comments/Assumptions
402.2.9
(FO7]1
Unvented crawl space wall R-
insulation R -value.
R- ❑Complies
See the Envelope Assemblies
R-
R- []Does Not
table for values.
*t
❑Not Observable
—�
❑Not Applicable
303.2
Unvented crawl space wall
❑Complies
[FO8]1
insulation installed per
❑Does Not
manufacturer's instructions.
❑Not Observable
❑Not Applicable
402.2.9
Unvented crawl space continuous
❑Complies
[FO9]1
vapor retarder installed over
❑Does Not
exposed earth, joints overlapped
by 6 in. and sealed, extending at
❑Not Observable
least 6 in. up and attached to the
❑Not Applicable
wall.
402.2.9
[FO10]1
Unvented crawl space wall in.
insulation depth of burial or
in. ❑Complies
See the Envelope Assemblies
distance from top of wall.
❑Does Not
table for values.
-
❑Not Observable
—
❑Not Applicable
303.2. z A protective covering is installed
❑Complies
[F011] to protect exposed exterior
❑Does Not
insulation and extends a
minimum of 6 in. below grade.
❑Not Observable
❑Not Applicable
403.8 Snow- and ice -melting system
❑Complies
[FO12]2 controls installed.
❑Does Not
❑Not Observable
❑Not Applicable
F+uumionat Lomments/Assumptions:
11 High Impact (Tier 1) 2 MediumImpact (Tier 2) 3 Low Impact (Tier 3)
Project Title: Landon & Kim McBride Report date: 10/21/19
Data filename:
Page 3 of 7
Section
#
Framing / Rough-In Inspection
Plans Verified
Field Verified
& Req.ID
Value
Value
Complies?
Comments/Assumptions
402.1.1,
402.3.1,
Glazing U-factor (area-weighted U-
average).
U_ ❑ Complies See the Envelope Assemblies
402.3.3,
[]Does Not table for values.
402.5
[]Not Observable
[FR2]1
❑Not Applicable
t?
303.1.3
U-factors of fenestration products
❑Complies
[FR4]1
are determined in accordance
❑Does Not
1,
with the NFRC test procedure or
taken from the default table.
[]Not Observable
[]Not Applicable
402.4.4
[FR20]1
Fenestration that is not site built
is listed
❑Complies
and labeled as meeting
❑Does Not
AAMA/WDMA/CSA 101/l.5.2/A440
or has infiltration rates per NFRC
❑Not Observable
400 that do not exceed code
❑Not Applicable
limits.
402.4.5 IC-rated
recessed lighting fixtures
❑Complies
[FR16]2 sealed at housing/interior finish
❑Does Not
I,
and labeled to indicate <_2.0 cfm
- leakage
at 75 Pa.
[-]Not Observable
❑Not Applicable
403.2.1 Supply ducts in attics are R-
[FR12]1 insulated to >_R-8. All other ducts
R- ❑Complies
H in
R-
unconditioned spaces or
R- ❑Does Not
outside the building envelope are
❑Not Observable
— insulated
to >_R-6.
❑Not Applicable
403.2.2 All joints and seams of air ducts,
❑Complies
[FR13]1 air handlers, filter boxes, and
❑Does Not
building
cavities used as return
ducts are sealed.
❑Not Observable
❑Not Applicable
403.2.3 Building cavities are not used for
❑Complies
[FR15]3 supply
ducts.
❑Does Not
:,.
❑Not Observable
❑Not Applicable
403.3 HVAC piping conveying fluids R_
R- ❑Complies
[FR17]2 above
105 °F or chilled fluids
❑Does Not
U. below
55 °F are insulated to >_R-
3•
❑Not Observable
❑Not Applicable
403.4 Circulating service hot water R- R- _ ❑Complies
[FR18]2 pipes
are insulated to R-2.
❑Does Not
❑Not Observable
❑Not
Applicable
403.5 Automatic or gravity dampers are
❑Complies
[FR19]2 installed
on all outdoor air
❑Does Not
intakes
and exhausts.
[]Not Observable
�NNn,-avic
Additional Comments/Assumptions:
1 I High Impact (Tier 1) 12 Medium Impact (Tier 2) 3 Low Impact (Tier 3)
i
Project Title: Landon & Kim McBride
Data filename:
Report date: 10/21/19
Page 4 of 7
Section
IPlans
#
Insulation Inspection
Verified
Value
Field Verified
Value
Complies?
Comments/Assumptions
& Re .ID
303.1
All installed insulation is labeled
❑Complies
[IN13]2
or the installed R-values
❑Does Not
provided.
❑Not Observable
❑Not Applicable
402.1.1,
Wall insulation R-value. If this is a
R-
R-
❑Complies See the Envelope Assemblies
402.2.4,
mass wall with at least 1/2 of the
❑ Wood
❑ Wood
❑Does Not table for values.
402.2.5
[IN3]1
wall insulation on the wall
exterior, the exterior insulation
E] Mass
mass
❑Not Observable
^
requirement applies.
E] Steel
Steel
❑Not Applicable
303.2
Wall insulation is installed per
❑Complies
[IN4]1
manufacturer's instructions.
❑Does Not
-
❑Not Observable
❑Not Applicable
Additional Comments/Assumptions:
11 High Impact (Tier 1) 12 Medium Impact (Tier 2) 13 1 Low Impact (Tier 3)
Project Title: Landon & Kim McBride Report date: 10/21/19
Data filename: Page 5 of 7
Section
Re .ID
F___
Final Inspection Provisions
Plans Verified
Value
Field Verified
Value
Complies?
Comments/Assumptions
402.1.1,
402.2.1,
Ceiling insulation R -value. Where
> R-30 is required, R-30 can be
R- R-
F-1 Wood F1 Wood
❑Complies See the Envelope assemblies
❑Does Not table for values.
402.2.2
[FI1]1
used if insulation is not
compressed at eaves. R-30 may
Steel Steel
❑Not Observable
,,
-
be used for 500 ft2 or 20%
❑Not Applicable
(whichever is less) where
sufficient space is not available.
303.1.1.1,
Ceiling insulation installed per
❑Complies
303.2
[FI2]1
manufacturer's instructions.
Blown insulation marked every
❑Does Not
300 ft2.
❑Not Observable
❑Not Applicable
402.2.3
[F13]1
Attic access hatch and door
insulation >R -value of the
R- R- ❑Complies
V,
adjacent assembly.
❑Does Not
❑Not Observable
❑Not Applicable
402.4.2, Building envelope tightness
402.4.2.1 verified by blower door test result
_
ACH 50 = ACH 50 = ❑Complies
[F117]1 of <7 ACH at 50 Pa. This
❑Does Not
requirement may instead be met
❑Not Observable
via visual inspection, in which
❑Not Applicable
case verification may need to
occur during Insulation
_ Inspection.
403.2.2 Post construction duct tightness
cfm cfm ❑Complies
[FI4]1 test result of 58 cfm to outdoors,
❑Does Not
or <12 cfm across systems. Or,
rough -in test result of s6 cfm
[]Not Observable
across systems or 54 cfm
❑Not Applicable
without air handler. Rough -in test
verification may need to occur
during FramingInspection.
_
403.1.1 Programmable thermostats
❑Complies
[F19] installed on forced air furnaces.
❑Does Not
❑Not Observable
[]Not Applicable
403.1.2 Heat pump thermostat installed
❑Complies
[FI10]2 on
heat pumps.
❑Does Not
❑Not Observable
❑Not Applicable
403.4 Circulating
service hot water
❑Complies
[FI11]2 systems have automatic or
❑Does Not
accessible
manual controls.
❑Not Observable
❑Not Applicable
404.1 50% of lamps in permanent
[FI6]1 fixtures are high efficacy lamps.
❑Complies
❑Does
Not
❑Not Observable
❑Not Applicable
401.3 Compliance certificate posted.
❑Complies
[F17]z
❑Does Not
❑Not Observable
❑Not
Applicable
303.3 Manufacturer manuals for
[FI18]3 mechanical and water heating
❑Complies
equipment have been provided.
❑Does
Not
❑Not
Observable
MAI
..4 A__1:__�1_
Additional Comments/Assumptions:
111 High Impact (Tier 1) 2 Medium Impact (Tier 2) 3 1 Low Impact (Tier 3)
Project Title: Landon & Kim McBride Report date: 10/21/19
Data filename:
Page 6 of 7
I I High Impact (Tier 1) 2 Medium Impact (Tier 2) 3 1 Low Impact (Tier 3)
Project Title: Landon & Kim McBride Report date: 10/21/19
Data filename: Page 7 of 7
�(2009 IECC Energy
j Efficiency Certificate
Above -Grade Wall 19.00
Below -Grade Wall 19.00
Floor 0.00
Ceiling / Roof 50.00
Ductwork (unconditioned spaces):
Window 0.28
Door 0.35
Heating System:
Cooling System:
Water Heater:
Name: Date•
Comments