Permit Status of (Open) as of Report Date: 09/30/2019 10:11 am
Permit Details Permit Number: 13-00228
525 S Center - BYUI Central Heating Plant
525 S Center
New Commercial Building
Permit Issued Date:
Permit Inspection Statistics
125Total Inspections Completed:
116Total Inspections Passed:
Inspection Pass Rate: 92.80%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
12/6/13 TD: Rebar for footings - rebar as per plans.Inspector Comments:
12/11/13 TD: Rebar for footing - footing and beam pads rebar as per plans.Inspector Comments:
1/27/14 TD: Footing/foundation - approved.Inspector Comments:
02/05/2014PassTed DyeFooting Inspection
2/5/14 TD: Rebar (footings and walls) - footing starting at grid g and grid 5.
Main electrical room.
Exterior grid to 5.37
Found DB pm 3 tonel counter clockwise to D & 3.8.
Inspector Comments:
Inspection scheduled for 1pm on small section on south end. Arrived early, but
already started pour (about 50% filled). Jacob, with Forsgren, was on site and
had inspected and found reinforcement to be good.
Inspector Comments:
02/26/2014PassQuinton OwensFooting Inspection
Previous rebar inspections approved on 1/7/14 and 1/13/14.Inspector Comments:
03/05/2014PassTed DyeFoundation Inspection
all rebar sized and spaced properly and held away from formInspector Comments:
03/14/2014PassQuinton OwensFooting Inspection
Footings on west side of building. Also partial Grade Beam and footings on south
east of existing heat plant.
Inspector Comments:
03/25/2014PassQuinton OwensFoundation Inspection
all rebar tied and correctly sized.
pushed away from forms when there
OK to pour
Inspector Comments:
03/31/2014PassQuinton OwensFoundation Inspection
Middle section of west wall.Inspector Comments:
03/31/2014PassQuinton OwensFooting Inspection
Footing for stairs on South end.Inspector Comments:
04/04/2014PassQuinton OwensFoundation Inspection
Missed due to scheduling error (requested for 4/3, not 4/4). Previous
observations at slab during other inspections showed no issues with insulation.
Special Inspector on site for pour said it all looked "good"
Inspector Comments:
Page 1 of 8
(Continued)
Permit Details Permit Number: 13-00228
525 S Center - BYUI Central Heating Plant
525 S Center
New Commercial Building
Permit Status of (Open) as of Report Date: 09/30/2019 10:11 am
Permit
Inspection
Summary
04/28/2014PassQuinton OwensFoundation Inspection
First four foot of interior masonry wall reinforcement bars in place and approved
for grout pour. Special Inspector on site.
Inspector Comments:
04/28/2014PassQuinton OwensFooting Inspection
Grade beam on north end of west wall and 2 spread footings on west end of
north wall. Approved for pour.
Inspector Comments:
04/29/2014PassQuinton OwensFoundation Inspection
Trench exterior Foundation on west end of North wall approved for pour.Inspector Comments:
05/07/2014PassQuinton OwensFoundation Inspection
Masonry grout pour. Inspection not scheduled at requested time. Special
Inspector verified compliance of work done.
Inspector Comments:
05/21/2014PassQuinton OwensFoundation Inspection
Masonry Grout for interior wall along grid D and grid C2 (between D1 & G), and
grid 4 between A & C). Also Exterior East wall at top from C to G (included single
#5 bar and embeds for connection to steel). Also viewed by special inspector.
Inspector Comments:
05/22/2014PassQuinton OwensFoundation Inspection
Grout pour on east half of south wall and some interior walls. Special Inspector
on site. Horizontal rebar in place.
Inspector Comments:
05/30/2014PassQuinton OwensFoundation Inspection
Slab on grade-2nd levelInspector Comments:
06/12/2014PassTed DyeFoundation Inspection
footing, floor combo on south end of building.Inspector Comments:
06/27/2014PassTed DyeFooting Inspection
Slab on grade.
Rebar is the correct size and spacing.
Approved to pour.
Inspector Comments:
06/27/2014PassTed DyeFoundation Inspection
Grout pour.
Horz.and vertical in place.
Special inspector on site.
Inspector Comments:
07/07/2014PassQuinton OwensFoundation Inspection
Block wall grout pour, west and north side exterior wall.Inspector Comments:
07/15/2014PassQuinton OwensFoundation Inspection
Masonry rebar & grout:
Not completely ready at inspection. Special Inspector will be checking just prior
to pour.
Inspector Comments:
08/26/2014PassQuinton OwensCommercial Insulation Inspection
wall between upper and lower roof on East Side insulated with vapor barrier
approved to cover.
Inspector Comments:
Page 2 of 8
(Continued)
Permit Details Permit Number: 13-00228
525 S Center - BYUI Central Heating Plant
525 S Center
New Commercial Building
Permit Status of (Open) as of Report Date: 09/30/2019 10:11 am
Permit
Inspection
Summary
06/26/2015PassQuinton OwensCommercial Footing Inspection
Footings between grid 3 and C1.2 and between H1 & CF (exlcluding spot footings
on grid 3.5 between J & H1).
Column pier rebar not in yet. Special Inspector to arrive for pour and will also
inspect rebar.
Inspector Comments:
07/10/2015PassQuinton OwensFoundation Inspection
Foundation between grids 3 and C1.2.Inspector Comments:
07/30/2015PassQuinton OwensCommercial Footing Inspection
Exterior footing from SW corner (grid H/2) to grid K/3, and foundation wall along
grid 3.6.
Inspector Comments:
08/04/2015PassQuinton OwensFoundation Inspection
Exterior foundation from SW corner (grid H/2) to grid K/3, and foundation wall
along grid 3.6.
Inspector Comments:
10/15/2015PassQuinton OwensCommercial Framing/Structure Inspection
Exterior overhang framing approved for cover.Inspector Comments:
10/20/2015PassQuinton OwensFoundation Inspection
Structural Masonry wall (west side of stairs to roof). Inspection of rebar at 4'
level. Complete special inspections as required.
Inspector Comments:
10/21/2015PassQuinton OwensFoundation Inspection
Masonry bond beam about 8' a.f.f.Inspector Comments:
10/22/2015PassQuinton OwensFoundation Inspection
Masonry bond beam at roof level.Inspector Comments:
11/09/2015FailQuinton OwensCommercial Framing/Structure Inspection
Steel stud framing approved, except for backing to be added for grab bars in
restrooms. Be sure toilet is centered 16" min. to 18" max. off side wall when
finished.
Inspector Comments:
12/09/2015PassQuinton OwensCommercial Sheetrock/Drywall Inspection
Missing screws in a few locations. Add as indicated to subcontractor. Hard
ceilings not hung yet.
Inspector Comments:
Inspected on 2/10: No areas over 1,000 sf. Tie wires at 4' o.c. and lights with 2
wires each.
Inspector Comments:
02/10/2016PassQuinton OwensSuspending Ceiling Inspection
Note prior to requesting final inspection:
Fire rated glass not installed as noted on plans, where is door fire rating label,
remember to complete handrails and guardrails in tunnel and at stairway "S03".
Inspector Comments:
Page 3 of 8
(Continued)
Permit Details Permit Number: 13-00228
525 S Center - BYUI Central Heating Plant
525 S Center
New Commercial Building
Permit Status of (Open) as of Report Date: 09/30/2019 10:11 am
Permit
Inspection
Summary
03/03/2016FailQuinton OwensCommercial Building Final
Restroom signage not installed. Sprinkler heads still have covers. 1 hour window
assembly does not have rated glass. No label on rated doors (104B, 112, 113C)-
Pre-Existing rated doors? Missing 2nd handrail and guardrail on stairs in tunnel
per plans. Exterior wall not finished around door to roof (door is also rated
without closer). Interior light in exit sign above door 113A is not working. Multiple
exterior doors are missing hardware. unprotected penetrations through rated wall
between boiler area and administrative area.
Inspector Comments:
03/03/2016PassQuinton OwensCommercial Framing/Structure Inspection
Re-inspectionInspector Comments:
03/11/2016FailQuinton OwensCommercial Building Final
** Approved for Temporary Occupancy only. **
Temporary non-ADA restroom signage installed. Missing 2nd handrail and
guardrail on stairs in tunnel per plans. Exterior wall not finished around door to
roof. Multiple exterior doors are missing hardware. Protect penetrations between
occupancies to resist the passage of smoke.
Inspector Comments:
05/17/2016PassQuinton OwensCommercial Building Final
Page 4 of 8
(Continued)
Permit Details Permit Number: 13-00228
525 S Center - BYUI Central Heating Plant
525 S Center
New Commercial Building
Permit Status of (Open) as of Report Date: 09/30/2019 10:11 am
Permit
Inspection
Summary
Electrical Inspection Type
01/13/2014Pass Electrical Underground Inspection
Approved for cover-underground conduit on SE corner of project for emergency
and control circuits to building on south end of project.
Inspector Comments:
01/14/2014PassBret StoddardElectrical Underground Inspection
01/14/2014PassBret StoddardElectrical Underground Inspection
Approved for cover for the next(middle) portion of conduit for the emergency and
control circuits on the east side of the project. This is the same inspection as the
other line with no notes-didn't save the first time.
Inspector Comments:
01/16/2014PassBret StoddardElectrical Underground Inspection
Approved for cover-underground conduit for emergency and control circuits-red
concrete installed because of shallow depth-16".
Inspector Comments:
02/05/2014PassBret StoddardElectrical Underground Inspection
Approved to place concrete-ufer-22' copper, concrete encased electrode.Inspector Comments:
02/20/2014PassBret StoddardElectrical Underground Inspection
02/24/2014PassBret StoddardElectrical Underground Inspection
03/07/2014PassBret StoddardElectrical Underground Inspection
03/12/2014PassBret StoddardElectrical Underground Inspection
03/19/2014PassBret StoddardElectrical Underground Inspection
04/01/2014PassBret StoddardElectrical Underground Inspection
04/07/2014PassBret StoddardElectrical Underground Inspection
04/08/2014PassBret StoddardElectrical Underground Inspection
04/10/2014PassBret StoddardElectrical Underground Inspection
04/11/2014PassBret StoddardElectrical Underground Inspection
04/14/2014PassBret StoddardElectrical Underground Inspection
05/05/2014PassBret StoddardElectrical Underground Inspection
05/07/2014PassBret StoddardElectrical Underground Inspection
05/19/2014PassBret StoddardElectrical Underground Inspection
05/28/2014PassBret StoddardElectrical Underground Inspection
05/30/2014PassBret StoddardElectrical Underground Inspection
06/03/2014PassBret StoddardElectrical Underground Inspection
06/10/2014PassBret StoddardElectrical Underground Inspection
Partial approval - grounding grid okay for cover, per Gabe Madrid.Inspector Comments:
Page 5 of 8
(Continued)
Permit Details Permit Number: 13-00228
525 S Center - BYUI Central Heating Plant
525 S Center
New Commercial Building
Permit Status of (Open) as of Report Date: 09/30/2019 10:11 am
Permit
Inspection
Summary
06/12/2014PassBret StoddardElectrical Underground Inspection
100' N of vault #1
250' S of vault #2 to vault #1
South side suspended slab an co-gen
All okay for cover partial approval, per Gabe Madrid.
Inspector Comments:
06/16/2014PassBret StoddardCommercial Electrical Rough-in
06/17/2014PassBret StoddardElectrical Underground Inspection
06/20/2014PassBret StoddardElectrical Underground Inspection
06/24/2014PassBret StoddardElectrical Underground Inspection
06/26/2014PassBret StoddardElectrical Underground Inspection
06/27/2014PassBret StoddardElectrical Underground Inspection
07/02/2014PassBret StoddardElectrical Underground Inspection
07/07/2014PassBret StoddardElectrical Underground Inspection
07/09/2014PassBret StoddardElectrical Underground Inspection
07/15/2014PassBret StoddardElectrical Underground Inspection
08/05/2014PassBret StoddardElectrical Underground Inspection
08/26/2014PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
08/28/2014PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
09/02/2014PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
09/04/2014PassBret StoddardCommercial Electrical Rough-in
09/19/2014PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
09/24/2014PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
10/06/2014PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
10/16/2014N/ABret StoddardElectrical Underground Inspection
10/21/2014PassBret StoddardCommercial Electrical Rough-in
11/07/2014PassBret StoddardElectrical Underground Inspection
11/17/2014PassBret StoddardCOM & MFR Electrical Service Inspection
12/04/2014PassBret StoddardElectrical Underground Inspection
12/09/2014PassBret StoddardElectrical Underground Inspection
12/10/2014PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
Page 6 of 8
(Continued)
Permit Details Permit Number: 13-00228
525 S Center - BYUI Central Heating Plant
525 S Center
New Commercial Building
Permit Status of (Open) as of Report Date: 09/30/2019 10:11 am
Permit
Inspection
Summary
02/27/2015PassBret StoddardElectrical Underground Inspection
underground at substation
**Completed by Jane Allred**
Inspector Comments:
03/10/2015N/ABret StoddardElectrical Underground Inspection
05/13/2015PassBret StoddardCOM, COM-A, COM-R, and COM-T Electrical Final Inspection
06/18/2015PassBret StoddardElectrical Underground Inspection
06/23/2015PassBret StoddardElectrical Underground Inspection
07/21/2015PassBret StoddardElectrical Underground Inspection
08/13/2015PassBret StoddardElectrical Underground Inspection
08/20/2015PassBret StoddardElectrical Underground Inspection
08/24/2015PassBret StoddardElectrical Underground Inspection
08/25/2015PassBret StoddardElectrical Underground Inspection
09/24/2015PassBret StoddardElectrical Underground Inspection
10/12/2015PassBret StoddardElectrical Underground Inspection
10/22/2015PassBret StoddardElectrical Underground Inspection
11/10/2015PassBret StoddardCommercial Electrical Rough-in
11/30/2015PassBret StoddardCommercial Electrical Rough-in
12/07/2015PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
02/04/2016PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
03/02/2016PassBret StoddardElectrical Final Inspection COM-A,R,T
Fire Inspection Type
04/07/2015PassBret StoddardFire Sprinkler Rough-in
04/09/2015PassDale PickeringFire Sprinkler Rough-in
05/07/2015FailBret StoddardFire Alarm Final Inspection
02/03/2016PassDale PickeringFire Sprinkler Final Inspection
02/03/2016PassDale PickeringFire Sprinkler Hydro
02/18/2016PassBret StoddardFire Alarm Final Inspection
Page 7 of 8
(Continued)
Permit Details Permit Number: 13-00228
525 S Center - BYUI Central Heating Plant
525 S Center
New Commercial Building
Permit Status of (Open) as of Report Date: 09/30/2019 10:11 am
Permit
Inspection
Summary
Mechanical Inspection Type
11/03/2014PassDon AllenHVAC Rough-in
The exhaust for the generator looks goodInspector Comments:
02/20/2015PassDon AllenHVAC Rough-in
duct work for the generator looks good.Inspector Comments:
03/03/2016FailDon AllenHVAC Final Inspection
THE GAS OUTLET FOR THE STOVE NEEDS A PLUG INSTALLED OR THE GAS
DTOVE HOOKED UP.
Inspector Comments:
05/18/2016PassDon AllenHVAC Final Inspection
Plumbing Inspection Type
03/20/2014PassDon AllenPlumbing Underground Inspection
good to cover 2nd ground workInspector Comments:
03/25/2014PassDon AllenPlumbing Underground Inspection
all good to cover storm lineInspector Comments:
04/11/2014PassDon AllenPlumbing Underground Inspection
ground work all good to coverInspector Comments:
07/31/2014PassDon AllenPlumbing Water
Water test started at 200 lb at 10:12 am and 12:10 was at 198 lbInspector Comments:
10/09/2014PassDon AllenPlumbing Rough-in
The low presser steam line held presser at 160 lbInspector Comments:
10/10/2014PassDon AllenPlumbing Rough-in
water for the boilers held at 160 lbInspector Comments:
02/13/2015PassDon AllenPlumbing Final Inspection
plumbingg good for the c/oInspector Comments:
08/24/2015PassDon AllenPlumbing Underground Inspection
GOOD TO COVER GROUND WORK IN THE BATHROOM.Inspector Comments:
11/25/2015PassDon AllenPlumbing Rough-in
central administration part of the building. dwv and the water are good to coverInspector Comments:
03/03/2016PassDon AllenPlumbing Final Inspection
GOOD FOR THE C/OInspector Comments:
Page 8 of 8