HomeMy WebLinkAboutINSPECTION SUMMARY - 13-00274 - 650 S 1st W - BYUI Student AptsPermit
Inspection
Summary
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Issued Date: 02/26/2014
Permit Inspection Statistics
182Total Inspections Completed:
142Total Inspections Passed:
Inspection Pass Rate: 78.02%
Permit Inspection History *Refer to Individual Inspection Report for more Details
04/24/2014PassDale PickeringWater Main Inspection - Site Plan
3/13 Hydrant Flow, Static @ 80psi, flow @ 76 psi, Pito @ 18Inspector Comments:
05/07/2014PassQuinton OwensFoundation Inspection
Northwest corner with 7 interior footings.Inspector Comments:
06/12/2014PassDon AllenPlumbing Underground Inspection
All good to cover the undergroundInspector Comments:
03/17/2015PassTed DyeSuspending Ceiling Inspection
Units 410, 413 and 415Inspector Comments:
04/28/2015PassQuinton OwensSuspending Ceiling Inspection
3rd floor corridor rating above hard ceilings.Inspector Comments:
09/04/2015PassJoel GrayPublic Works Final Inspection
Pass with the following conditions:
1. Flow meter for sanitary sewer is installed shortly.
2. Manhole lids are corrected for utility it serves.
3. Bollards are needed behind each dumpster.
Inspector Comments:
Page 1 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
Building Inspection Type
03/28/2014PassQuinton OwensFooting Inspection
Middle section of west wing. Special Inspector on site for concrete testing.Inspector Comments:
04/09/2014PassQuinton OwensCommercial Footing Inspection
Footing at middle section of south wing (Grid 6-8). Special inspector onsite.Inspector Comments:
05/21/2014PassQuinton OwensFoundation Inspection
Elevator shaft and small portion of connecting foundation walls and section on
west end of north wall. Fix clearance to top rebar of west end of north wall pour.
(came by during pour - special inspector will make sure clearance is fixed)
Inspector Comments:
05/28/2014PassQuinton OwensFoundation Inspection
6 Spot footings in NW corner, and foundation wall along grids A, B, & C from grid
6 to 8. Special inspector on site.
Inspector Comments:
05/30/2014PassTed DyeFoundation Inspection
spot footings on north end of building C and on center foundationInspector Comments:
06/05/2014PassQuinton OwensFoundation Inspection
Foundation wall along grids A, B, & C from grid 8 to 9. Special inspector on site.Inspector Comments:
06/12/2014PassTed DyeFooting Inspection
footing on north side of buildingInspector Comments:
06/25/2014PassQuinton OwensFoundation Inspection
Center and North walls of middle section of North wing.Inspector Comments:
06/25/2014PassQuinton OwensFooting Inspection
South footing of middle section of North wingInspector Comments:
07/07/2014PassQuinton OwensFooting Inspection
Interior footings from center stair to grid E.A. Approved for pour. Special
inspector on site for pour.
Inspector Comments:
07/07/2014PassQuinton OwensFoundation Inspection
South exterior foundation wall from central stairs to grid E.A approved for pour.
Special inspector on site for pour.
Inspector Comments:
07/15/2014PassQuinton OwensCommercial Footing Inspection
Footing inspection for East end of East wing.(grid F-H). Special inspector was on
site.
Inspector Comments:
07/15/2014PassQuinton OwensFoundation Inspection
Foundation inspection at Mid-section of East wing (grid D-F). Special Inspector on
site.
Inspector Comments:
Interior walls and South and East end exterior walls on East wing. Special
Inspector on site.
Inspector Comments:
07/25/2014PassQuinton OwensFoundation Inspection
7/24: North half of East wing (interior & North Ext walls approved)Inspector Comments:
Page 2 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
07/31/2014PassQuinton OwensCommercial Footing Inspection
Exterior stairs (not for building). Done as per shop drawings. Civil drawings lack
details. 3 bars continuous (not connected at footing steps) with vertical dowels in
place. Approved for pour.
Inspector Comments:
01/09/2015PassQuinton OwensCommercial Framing/Structure Inspection
Perimeter of south wing roof sheathing (south end up to 3rd living rm popout-
almost to stairwell).
Inspector Comments:
01/13/2015PassQuinton OwensCommercial Framing/Structure Inspection
Roof sheathing inspection on South wing.Inspector Comments:
01/26/2015PassQuinton OwensSheeting
North wing from grid A to F inspected (From Stairs to East end not ready).Inspector Comments:
01/28/2015PassTed DyeSheeting
Area of inspection was from South east corner of building A , South end, from
corner west to first inside corner.
On the East wall, area of inspection was from S.East corner, north to the other
side of the first bump out.
All area's passed
Inspector Comments:
01/29/2015FailTed DyeSheeting
those places that missed being nailed are marked with green paint both inside
and outside where possible, but always inside.
Inspector Comments:
01/30/2015FailTed DyeSheeting
Sheeting that missed being nailed to studs area;
A 110 Around window area athat needs leveling
A 108 aea marked with paint. Also the bottom of the second sheets have missed
being nailed.
A 210 and 308 have sheeting that missed being nailed.
**There are area's on the whole building(East side inspected) that do not have
enough nails along the seams or in the field.
Inspector Comments:
02/03/2015PassTed DyeSheeting
The East wall(DA-1) from9A to 6A pop out is approved for cover. all levelsInspector Comments:
02/04/2015PassTed DyeSheeting
Roof sheeting above commons; checked the nailing around the out side 4 feet
only. The middle section will have an inspection called in at a later date.
Inspector Comments:
02/10/2015FailQuinton OwensSheeting
Inspected sheathing on West side 4th floor from South End to 4th pop out
(corrections made during inspection and approved). West side 2nd & 3rd floor
sheathing approved from South end up to and including 2nd pop out. West side
1st floor sheathing from South end to 2nd pop out has multiple lines of nails
penetrating too deep.
Inspector Comments:
Page 3 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
02/11/2015FailQuinton OwensCommercial Framing/Structure Inspection
4th level exterior walls and roof framing in first 4 units on south end (417, 415,
412, & 410 (?)). Ok to insulate and reinspect when ready.
Inspector Comments:
02/12/2015PassQuinton OwensSheeting
West wall levels 2, 3, & 4. Needed corrections (partial stud nailing/some
blocking) marked with green paint on inside. May reinspect with 1st level. Okay
to hang windows.
Need inspection done on 1st level when ready.
Inspector Comments:
02/13/2015Fail Sheeting
Unit 313: Sheeting missed being nailed to stud.
Hallway: Stud in corner missed being nailed.
Unit 307: One stud in N.W. corner missed being nailed.
Unit 207: Needs blocking added and nailed
One stud missed being nailed.
Unit 213: Stud in 2nd bedroom missed being nailed.
Unit 215: First and Second bedrooms had sheeting that was not nailed.
Unit 217: Last bedroom has a stud that sheeting was not nailed too.
Unit 113: 2nd bedroom had a stud that the sheeting was not nailed too.
Unit 109: Living room was missing a piece of sheeting in the N.W.corner(bump
out).
Inspector Comments:
02/17/2015PassTed DyeCommercial Insulation Inspection
02/18/2015FailTed DyeSheeting
Units 401 and 402 have sheeting in corners on east wall that need to be nailed to
studs.
Unit 403 had sheeting at the bump out that needed to be nailed to studs.
Inspector Comments:
02/18/2015FailQuinton OwensCommercial Framing/Structure Inspection
Exterior walls and roof framing prior to insulation for Apt's 413, 411, 408, & 406.
Add drywall backing in corner and additional header above window in living room
of 411. Two nuts to be tightened on steel column anchor bolts in corner of Apt
406. Finish fire blocking electrical penetrations (including extra holes) at roof joist
above rated walls in 411 & 406. Be sure studs have full contact with plates in
bearing walls. Shim gaps as needed.
OK TO INSULATE IF FRAMING ITEMS ARE VISIBLE TO RE-INSPECT WITH
INSULATION.
Inspector Comments:
02/18/2015PassQuinton OwensCommercial Insulation Inspection
Exterior walls & Roof insulation in Apt's 415 & 410.Inspector Comments:
02/20/2015FailQuinton OwensCommercial Framing/Structure Inspection
Apartment 411 header & drywall backing done. Earthbound system incomplete in
SW corner of living rm.
OK to insulate Roof & ext. wall except at Earthbound location in 411.
Inspector Comments:
Page 4 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
02/20/2015PassQuinton OwensCommercial Insulation Inspection
insulation in apartments 408 and 413 approved.Inspector Comments:
02/23/2015PassQuinton OwensCommercial Insulation Inspection
Apt. 411 Insulation approved, Finish installing Vapor barrier.Inspector Comments:
02/23/2015PassQuinton OwensCommercial Framing/Structure Inspection
Exterior framing items done in Apt 406. Common area framing on south end
approved for insulation.
Inspector Comments:
02/24/2015PassQuinton OwensCommercial Insulation Inspection
Apt. 406 insulation and vapor barrier completed. (411 vapor barrier done).
Party wall sound insulation completed between south wing apartments.
Inspector Comments:
02/24/2015FailQuinton OwensCommercial Framing/Structure Inspection
Apt 409 Exterior walls and Roof framing prior to insulation.
Multiple bearing cripple studs above living room window have gaps, not bearing,
on window header.
INTERIOR BEARING walls of other south wing apartments have same issue
above multiple door headers.
Inspector Comments:
02/26/2015FailQuinton OwensCommercial Framing/Structure Inspection
Exterior wall and ceiling framing of 317, 315, 312, 310. Walls insulated. Joists at
shaft corners to be rated at gap between drwall and web. Fire block/caulk still to
be done at party walls. Subs not completed with other items within floor cavities.
Inspector Comments:
03/03/2015PassTed DyeCommercial Framing/Structure Inspection
Framing inspection on top floor only. (North wing)Inspector Comments:
03/05/2015PassTed DyeCommercial Insulation Inspection
03/06/2015PassQuinton OwensCommercial Framing/Structure Inspection
Units 317, 315, 312, 310 Floor/Ceiling framing above and Exterior wall framing
only.
315, 312, & 310 need to complete rating gap at web joist cavity by shaft to
mechanical room.
Inspector Comments:
03/06/2015PassTed DyeCommercial Framing/Structure Inspection
03/10/2015FailQuinton OwensCommercial Insulation Inspection
401, 402, 403: Fire rating at shafts not extended up to roof deck. Other areas
approved for cover.
Inspector Comments:
03/12/2015FailQuinton OwensCommercial Insulation Inspection
Finish taping joints in concealed locations in 313, 308, and in end bathroom of
306. Be sure shafts are rated on both sides of joist above pantry and joints are
taped.
Rest of apartment areas ok for drywall.
Inspector Comments:
Page 5 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
03/13/2015PassQuinton OwensSuspending Ceiling Inspection
417 & 412 drywall approved to tape & hang lower ceiling.
Be sure screw spacing is 12" on center. Several large gaps are occurring. Finish
patching shaft for fire rating up to roof deck on 401, 402, 403, and on hallway
side wherever incomplete.
Inspector Comments:
03/13/2015PassQuinton OwensCommercial Insulation Inspection
Re-inspection: 3rd floor, South wing apartments approved for hangingInspector Comments:
03/17/2015FailTed DyeCommercial Framing/Structure Inspection
406 & 411 drywall and upper ceilingpenetrations:
411 needs added screws in bedroom closets, fire caulk sprinkler pipe in wall / fire
rate gap in ceiling of last bathroom, fire caulk penetrations in top plate behind
bathroom vanities, and finish upper ceiling in pantry closet.
406 fire caulk around PVC pipe in kitchen north wall and above bathroom
vanities, fire rate roof drain penetrations, fire rate gap at edge of pantry ceiling.
Inspector Comments:
03/18/2015FailQuinton OwensCommercial Sheetrock/Drywall Inspection
North wing 4th floor cooridor needs mechanical shaft finished up to roof deck on
side by unit entry doors.
Inspector Comments:
03/18/2015N/AQuinton OwensCommercial Framing/Structure Inspection
Changed to drywall inspection and upper ceiling penetrations.Inspector Comments:
03/19/2015Pass Commercial Sheetrock/Drywall Inspection
Units 310, 312, 315 and 317 had sheetrock and fire caulking in the concealed
area above the lowered ceiling checked and it passed.
Inspector Comments:
03/20/2015PassQuinton OwensCommercial Insulation Inspection
Units 313, 311, 309, 308, 307, 306, 305, 304, 303, 302, 301 Insulation approved.
301 fire rating behind bathtub in concealed location to be inspected before
covering.
Inspector Comments:
03/25/2015FailTed DyeCommercial Framing/Structure Inspection
Two layers of drywall not installed in units above linen and entry closet are 206,
209, 210, 212, 213 and 215.
Inspector Comments:
03/26/2015FailTed DyeCommercial Framing/Structure Inspection
206,210,215 AND 411 Tape those area that had the second layer of drywall
installed.
211 drywall 2nd layer missing above linen closet.
213 drywall 2nd layer missing right of electrical panel.
208, 212 OK.
Inspector Comments:
04/01/2015PassTed DyeCommercial Sheetrock/Drywall Inspection
04/02/2015PassTed DyeCommercial Insulation Inspection
Insulation inspection in units 6, 8, 9, 10, 11, 12, 13, 15 and 17Inspector Comments:
Page 6 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
04/03/2015PassTed DyeCommercial Framing/Structure Inspection
Units 201, 202, 203, 204, 205 and 207 framing approved.Inspector Comments:
04/10/2015PassTed DyeCommercial Insulation Inspection
Units Inspected; 201, 202, 203, 204, 205and 207. PassedInspector Comments:
04/13/2015PassQuinton OwensCommercial Framing/Structure Inspection
level 3 partialInspector Comments:
04/13/2015PassQuinton OwensCommercial Insulation Inspection
level 2 north wingInspector Comments:
04/14/2015N/AQuinton OwensCommercial Framing/Structure Inspection
Wrong permit: Inspection is for Building CInspector Comments:
Page 7 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
04/17/2015FailTed DyeCommercial Framing/Structure Inspection
Building A
******************************Typ. All
Units;********************************
-Electrical mains have not been pulled. When they are, fire caulking will need to
be done @ the separation walls and above the electrical panel.
-In the front entry closet there is a flex conduit that needs fire caulked at the top
plate.
-Fire caulk around those areas of the TJI's that the rock wool was not able to fill.
---Unit 117 See above notes.
---Unit 112 See above notes.
---Unit 115 See above notes.
Fire caulk electrical wires in north bedroom, located in prerock in TJI's
---Unit 110 See above notes.
---Unit 113 See above notes
Dywall missing at south separation wall in TJI cavity.
---Unit 108 See above notes.
Hole in prerock in back bathroom in the TJI cavity at the separation
wall.
---Unit 111 See above notes.
Patch drywall in back bedroom in the TJI cavity at the separation
wall.
All electrical wiring not complete to include smurf tube and wiring for
exterior lights.
---Unit 106 See above notes.
TJI joist hanger is not attached properly.
Patch prerock in back bedroom in TJI cavity at the separation wall.
Drywall is not complete at the separation wall in the TJI cavity.
---Unit 109 See above notes.
Entry closet hole in top plate.
In back bathroom patch drywall in TJI cavity on separation wall.
Fire caulk around TJI in back bathroom at the chase wall.
In back bedroom, fire caulk around smurf tube and fire alarm wires
in TJI cavity on sepation wall.
Fire caulk electrical wires on exterior wall in back bedroom and in
closet.
Finish Shear wall then drywall in TJI cavity on south separation wall
Fire caulk electrical wires on south separation wall.
Inspector Comments:
04/17/2015PassQuinton OwensCommercial Framing/Structure Inspection
Center Stair Enclosure approved for insulation.Inspector Comments:
04/17/2015PassQuinton OwensCommercial Insulation Inspection
Top level of elevator shaft insulation.Inspector Comments:
Page 8 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
04/17/2015FailQuinton OwensCommercial Sheetrock/Drywall Inspection
3rd floor north wing and 309: upper pantry closets not taped or not fire caulked
or not drywalled. Shaft wall in closet by bathroom (all units) have "not type x"
drywall which does not provide correct fire rating. Properly fire caulk around
ceiling penetrations in 302 (east side of kitchen). Missing screws in various
locations.
Ok to hang lower ceiling in main areas only, but NOT in any pantry closet or
closet by bathroom.
Inspector Comments:
04/20/2015FailQuinton OwensCommercial Framing/Structure Inspection
Work in progress on rated assemblies in concealed locations. Finish taping joints.
Double layer drywall required on all ceilings, even in concealed locations. Finish
sealing gap at joist web on shaft walls and drywall outside entry doors for 2 hr
rating.
Ok to insulate where corrections can be reinspected with insulation.
Inspector Comments:
04/21/2015FailQuinton OwensCommercial Framing/Structure Inspection
East Stair framing, South Stair framing, and South wing 1st level anchor bolt
re-inspect.
Missing all nuts & washers on one side of column by window on 3rd floor landing
(South stairs)
Missing stud on 3rd floor landing behind kitchen of 302.
1st Floor south wing: Several anchor bolts need tightening and/or epoxied.
missing stud on party wall in 110 & 115.
Inspector Comments:
04/21/2015PassQuinton OwensCommercial Insulation Inspection
Middle stair insulation. Avoid compressing insulation.Inspector Comments:
04/22/2015FailQuinton OwensCommercial Framing/Structure Inspection
First floor north wing framing along with Reinspect framing on South & East
stairs and 1st floor anchor bolts in south wing.
North wing: Fire caulk missed penetrations in 102 and 107. Fire rate between
joists on bathroom side of shaft in 107. Anchor bolts not completed.
East and south stairs framing APPROVED. Anchor bolts on south wing 1st floor
completed.
Inspector Comments:
04/24/2015PassQuinton OwensCommercial Insulation Inspection
04/24/2015PassTed DyeCommercial Framing/Structure Inspection
Inspected anchor bolts and Firecaulking missed on 1st inspection on units 102
and 107.Also checked anchor bolts that were missed on the north wing.
Inspector Comments:
04/28/2015PassQuinton OwensCommercial Insulation Inspection
South stair tower insulation (finish vapor barrier on 1st & 2nd floor landing)Inspector Comments:
04/29/2015PassTed DyeCommercial Insulation Inspection
Page 9 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
04/29/2015FailTed DyeCommercial Framing/Structure Inspection
There is a question on the location of handicap door openers in the west
basement entrance.
Willlook up that [information and get back with you.
Inspector Comments:
04/30/2015PassTed DyeCommercial Sheetrock/Drywall Inspection
Units inspected and passed are;
206, 208, 210, 212, 211, 213, 215 and 217
Inspector Comments:
05/05/2015PassQuinton OwensCommercial Sheetrock/Drywall Inspection
201, 203, 204, 205, & 207 drywall approved.
202 requires 2 layers on wall common with stair enclosure.
Inspector Comments:
05/05/2015PassQuinton OwensCommercial Sheetrock/Drywall Inspection
Only 201, 203, 204, 205, 207 Drywall approved to tape & hang lower ceiling.
WATCH FASTENER SPACING. (12" o.c. max).
202 missing 2nd layer on stair enclosure wall (re-inspect - including above
dropped ceiling).
Inspector Comments:
05/06/2015PassQuinton OwensCommercial Sheetrock/Drywall Inspection
Level 2 corridor drywall above dropped hard ceilings approved.
Corrections in other areas: properly fire caulk around pipe above entry door to
201 and where same pipe enters rated shaft just inside 201. Add screws for
proper spacing in rest of 2nd floor corridor.
Inspector Comments:
05/06/2015PassQuinton OwensCommercial Insulation Inspection
Basement Insulation approved. Replace insulation where work is currently being
done. One hole found needing fire caulk in top plate on north side of corridor.
Inspector Comments:
05/15/2015PassTed DyeCommercial Sheetrock/Drywall Inspection
Units inspected for fire caulk above dropped ceiling, bearing wall, and the main
drywall inspection are: 106, 107, 108, 109, 110, 111, 112, 113, 115, and 117.
All passed. Ok to hang drywall on dropped ceiling.
Inspector Comments:
05/22/2015FailQuinton OwensCommercial Sheetrock/Drywall Inspection
Some screws missing, some locations need backing, some are spaced too far, a
couple locations have exposed structural element to be covered.
Inspector Comments:
05/29/2015FailTed DyeCommercial Sheetrock/Drywall Inspection
-Inspected all corridors on level one.
-The lobby on the east end of building was not readdy for an inspection, work
still being done
Inspector Comments:
Page 10 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
06/08/2015PassQuinton OwensCommercial Sheetrock/Drywall Inspection
Units 102 - 105 completed without reinspection of previous items. Dan verified
structural steel was covered as indicated. Drywaller said screws have been added
where missed.
Drywall in all stairs approved (Fire barrier in center stairs is covered by furred out
wall).
Re-inspection of 1st floor corridor: Sprinkler pipe by center stair covered with
drywall since it interupted the original layers. Other corrections in corridor are
above acoustical ceiling and will re-inspect after grid is installed.
Inspector Comments:
06/25/2015FailQuinton OwensCommercial Sheetrock/Drywall Inspection
First floor common area at east end of building. Inspection request called in late;
Drywall taping mostly done (could not inspect drywall type). Several penetrations
to be fire rated - at fire rated assemblies. Plastic pipes MUST have fire caulk
INSIDE ANNULAR SPACE. Fire riser pipe next to south stair enclosure must have
penetrations fire rated and inspected. Steel column fire rating incomplete. Tape
and rate drywall inside new enclosed mailbox location.
Inspector Comments:
06/30/2015FailQuinton OwensCommercial Sheetrock/Drywall Inspection
1st level common area reinspect. Column fire rating correction incomplete (slide
drywall behind insulated pipe and tape). fire caulk perimeter of duct penetration
into mechanical room.
Inspector Comments:
07/02/2015PassQuinton OwensCommercial Sheetrock/Drywall Inspection
4th floor corridor drywall & penetrations above ceiling tiles.Inspector Comments:
07/08/2015FailQuinton OwensCommercial Sheetrock/Drywall Inspection
3rd floor corridor drywall approved above tile ceiling areas.
Patch open hole in 2 hr rated stair wall behind fire riser pipe on 3rd floor (Lower
floors to be inspected in same area).
Inspector Comments:
07/22/2015FailQuinton OwensCommercial Sheetrock/Drywall Inspection
2nd floor corridor above grid ceiling: Fire caulk gaps at duct penetration next to
212 and 201. Seal holes left from missed hanger placement.
Inspector Comments:
07/23/2015PassQuinton OwensCommercial Sheetrock/Drywall Inspection
Reinspect 2nd floor corridor: Ceiling area penetrations and ducts by 212 & 201
completed. Fire riser fire caulked at penetration into stairwell. Corridor only
approved & 4th floor music room ceiling on south end.
Ceilings in rooms at east end have open holes to be fire caulked and fire rate
recessed box on stair wall to be rated (have these reinspected).
Inspector Comments:
Page 11 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
07/24/2015FailQuinton OwensCommercial Sheetrock/Drywall Inspection
First floor common area at east end. Fire riser concealed cavity needs to be
taped and have penetrations fire caulked on ceiling, south wall (stairs), and west
wall (apt).
Structural column at east end of corridor completed for fire rating behind
insulated pipe, but still have duct penetrations into mechanical room (by north
exterior door) to fire rate.
Inspector Comments:
08/05/2015FailQuinton OwensCommercial Sheetrock/Drywall Inspection
1st floor common area (east end). fire rate duct penetration in room north of
mailbox location.
Inspector Comments:
08/10/2015PassQuinton OwensCommercial Sheetrock/Drywall Inspection
1st floor corridor/common area only - approved to cover upper rated ceiling.Inspector Comments:
08/20/2015FailQuinton OwensCommercial Building Final
Items needed for temp C.O.:
Finish fire rating penetrations in rated assemblies.
90 min rated glazing required in interior stair enclosure doors.
Fire "block" open ended conduits connecting floors at data room.
Apt.numbers not posted on first level.
Stair identification signage not posted.
Exterior stair handrails to be completed or stairs barricaded.
Corrections needed for full C.O.:
Parking to be completed.
Finish exterior vent terminations.
Walls around mop sinks to be finished as per code.
Building identification to be posted.
Sidewalk slopes by east entry are under review.
Inspector Comments:
09/04/2015PassQuinton OwensSidewalk Inspection
No inspections requested for sidewalks prior to concrete pours. "Finished"
installation approved.
Inspector Comments:
09/10/2015FailQuinton OwensCommercial Building Final
Install parking signs for the 2 added handicap stalls.
Sidewalk slopes by east entry to be fixed after dedication.
Note: Must add missing vertical grab bar in tub/shower (A102) when utilized for
accessibility.
Inspector Comments:
10/22/2015PassQuinton OwensCommercial Building Final
Drive by inspection: H.C. parking signs installed and sidewalk corrected.
Approved for complete C.O.
Inspector Comments:
Page 12 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
Electrical Inspection Type
08/25/2014PassBret StoddardElectrical Underground Inspection
Approved to backfill duct bank on east side of first building across temporary
driveway in the north east corner of the project.
Inspector Comments:
09/02/2014PassBret StoddardElectrical Underground Inspection
02/11/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
02/17/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
02/18/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
02/19/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
02/25/2015PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
02/26/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
02/27/2015PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
03/03/2015PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
4th Floor Building A
N corridors only
3rd floor units 313 &308
**Completed by Jane Allred**
Inspector Comments:
03/04/2015PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
03/09/2015PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
03/12/2015PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
03/13/2015PassBret StoddardCOM-A, COM-R, COM-T Electrical Rough-in
03/16/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
03/17/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
03/19/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
03/24/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
04/01/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
04/02/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
04/09/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
04/10/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
04/15/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
04/16/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
Page 13 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
04/17/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
04/21/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
04/23/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
04/28/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
04/30/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
05/05/2015PassBret StoddardCommercial Electrical Rough-in
05/14/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
05/21/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
05/29/2015PassBret StoddardSFR-A,R,B, MFR,MFR-A,R Electrical Rough-in
07/08/2015PassBret StoddardSFR, SFR-B, SFR-A, SFR-R, MFR, MFR-A, MFR-R Electrical Final Inspection
08/04/2015PassBret StoddardSFR, SFR-B, SFR-A, SFR-R, MFR, MFR-A, MFR-R Electrical Final Inspection
08/06/2015PassBret StoddardSFR, SFR-B, SFR-A, SFR-R, MFR, MFR-A, MFR-R Electrical Final Inspection
08/12/2015PassBret StoddardSFR, SFR-B, SFR-A, SFR-R, MFR, MFR-A, MFR-R Electrical Final Inspection
08/19/2015PassBret StoddardSFR, SFR-B, SFR-A, SFR-R, MFR, MFR-A, MFR-R Electrical Final Inspection
Page 14 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
Fire Inspection Type
02/26/2014PassDale PickeringFire Underground Inspection
03/11/2015N/ABret StoddardFire Sprinkler Hydro
03/23/2015PassDale PickeringFire Sprinkler Hydro
03/23/2015PassDale PickeringFire Sprinkler Hydro
04/09/2015PassDale PickeringFire Sprinkler Hydro
04/09/2015PassDale PickeringFire Sprinkler Hydro
04/09/2015PassDale PickeringFire Sprinkler Hydro
04/09/2015PassDale PickeringFire Sprinkler Rough-in
Building A, 1st floor rough-in, PassInspector Comments:
04/29/2015PassDale PickeringFire Sprinkler Hydro
Building A Standpipe hydro and rough-in/cabinets; PassInspector Comments:
06/04/2015PassDale PickeringFire Sprinkler Hydro
08/12/2015PassDale PickeringFire Sprinkler Rough-in
Basement, 4 heads only, David DavisInspector Comments:
08/14/2015N/ABret StoddardFire Alarm Final Inspection
08/18/2015PassBret StoddardFire Alarm Final Inspection
08/19/2015PassDale PickeringFire Sprinkler Final Inspection
09/03/2015PassDale PickeringFire Department Final Inspection
Page 15 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
Mechanical Inspection Type
08/15/2014PassDon AllenHVAC Rough-in
All good to cover the under ground on the hvacInspector Comments:
02/17/2015PassDon AllenHVAC Rough-in
All good to cover the duct work on the 2nd floor in the apt.Inspector Comments:
03/04/2015PassQuinton OwensHVAC Rough-in
Apt. 415, 413, 411, 410, 408, 406: Exhaust and Mech. room shaft penetrations
and ducts inspected.
Inspector Comments:
03/13/2015PassDon AllenHVAC Rough-in
On the south end of building a the 1st 3 rooms on the 4th floor ar good to coverInspector Comments:
03/17/2015PassDon AllenHVAC Rough-in
rooms 4-7 on bld a on floor 4 in the wing that runs north and south are good to
cover
Inspector Comments:
03/17/2015PassDon AllenHVAC Rough-in
Bld. A 4th floor the wing that runs north and south all rooms good to cover.Inspector Comments:
03/19/2015PassDon AllenHVAC Rough-in
The first 4 apt on the 3 floor starting on the south are good to coverInspector Comments:
04/01/2015PassDon AllenHVAC Rough-in
the hvac in thefirst 4 rooms on the 4th floor that run west to east are good to
cover. Still need to look at the chases that run floor to floor. On the bottom 1st
floor the chases in the rooma and mech. rooms that run north to south are also
good.
Inspector Comments:
04/08/2015PassDon AllenHVAC Rough-in
hvac on the 4th floor mech. chases are good to coverInspector Comments:
04/16/2015PassDon AllenHVAC Rough-in
All the chases in the hallway and apt. on the 3 floor of building A are good to
cover.
Inspector Comments:
04/17/2015PassDon AllenHVAC Rough-in
ALL THE ROOMS ON THE 3 FLOOR CAN BE COVERED EXCEPT THE 4 BED ROOM
ON THE NORTH WEST CORNER OF THE BUILDING.
Inspector Comments:
04/24/2015PassDon AllenHVAC Rough-in
ALL THE CHASES IN THE ROOMS AND MECH. ROOMD ARE GOOD TO COVERInspector Comments:
04/27/2015FailDon AllenHVAC Rough-in
NEED TO FINISH FIRE CAULKINGInspector Comments:
05/01/2015PassDon AllenHVAC Rough-in
All the rooms on the 2nd floor hallway that run north to south are good to cover.Inspector Comments:
Page 16 of 17
(Continued)
Permit Details Permit Number: 13-00274
650 S 1st W - BYUI Student Apts, Bldg A; 59 Units
650 S 1st W
New Multi-Family Residential/Dormitory
Permit Status of (Open) as of Report Date: 09/25/2019 12:00 pm
Permit
Inspection
Summary
08/21/2015PassDon AllenHVAC Final Inspection
good for the tepm. c/oInspector Comments:
09/03/2015PassDon AllenHVAC Final Inspection
GOOD FOR THE C/OInspector Comments:
Plumbing Inspection Type
08/15/2014PassDon AllenPlumbing Underground Inspection
02/17/2015PassDon AllenPlumbing Rough-in
mop sinks are good to cover on all floorsInspector Comments:
02/20/2015PassDon AllenPlumbing Rough-in
the 4 units on the 4th and 3rd floor on the section that runs east and west held
presser on the dwv.
Inspector Comments:
03/18/2015PassDon AllenPlumbing Rough-in
Plumbing roughin on the 2nd floor of bld.A is good to coverInspector Comments:
04/08/2015PassDon AllenPlumbing Rough-in
plumbing roughin on the 1 floor is good to coverInspector Comments:
04/27/2015PassDon AllenPlumbing Water
WATER LINE HELD AT 100 LBInspector Comments:
05/22/2015PassDon AllenPlumbing Rough-in
gas and water line on the 1st floor held testInspector Comments:
07/31/2015PassDon AllenPlumbing Final Inspection
GOOD FOR THE C/OInspector Comments:
08/21/2015PassDon AllenPlumbing Final Inspection
Page 17 of 17