HomeMy WebLinkAboutINSPECTION TICKETS - 18-00479 - 40 W 7th N - Basic American New Building AdditionMadison County
Building Department
134 E Main
Rexburg, Idaho 83440
INSPECTION TICKET
Basic American Foods:
4/3/19
OFFICE COPY
I, Ralph Robison met with Ted Dye (City of Rexburg Inspector). We went out to
BAF and met with Site manager from Mass. from Dennis Group. We toured progress of job
sight.
Working on grading (on going)
Electrical conduits backfilled
Drain lines installed and back filled
Poured most of the footings and foundation
On the East side. They almost have the premiter
Completed. Should have prep for 8" slabs this
Coming week
Setting up forms next to existing building
Site prep for North side receiving area completed
Ralph Robison
Madison County
Building Inspector
Madison County
Building Department
134 E Main
Rexburg, Idaho 83440
INSPECTION TICKET
Basic American Foods:
3/27/19
OFFICE COPY
I, Ralph Robison met with Ted Dye (City of Rexburg Inspector). We went out to
BAF and met with Travis Tripp from Dennis Group. We toured progress of job sight.
Working on grading (on going)
Electrical conduits backfilled
36 " deep slab poured
Cure time was 28 days Plus so moving ahead with slab pour
They had completed south side of slab
Setting up forms next to existing building
Doing grub work on North side (receiving area
,a c� �O
Ralph Robison
Madison County
Building Inspector
Madison County
Building Department
134 E Main
Rexburg, Idaho 83440
INSPECTION TICKET
Basic American Foods:
3/19/19
OFFICE COPY
I, Ralph Robison met with Ted Dye (City of Rexburg Inspector). We went out to
BAF and met with Travis Tripp from Dennis Group. We toured progress of job sight.
Working on grading (on going)
Electrical conduits underground to be covered up
36 " deep slab 8" grid pattern double, top and bottom pattern
Cure time was 28 days Plus so moving ahead with slab pour
They were forming south side of slab.
Ralph Robison
Madison County
Building Inspector