HomeMy WebLinkAboutINSPECTION TICKET - 19-00359 - 871 Jet Stream Dr - The Rock Gym - New CommercialInspection
Ticket
Building Review on 07/01/2019:
Permit Number: 19-00359Permit Details
Building - Commercial
Permit Issued Date:
Permit Issued Date: Final Inspections Required
Fire Sprinkler Final Inspection HVAC Final Inspection
Plumbing Final Inspection Fire Department Final Inspection
Public Works Final Inspection Fire Alarm Final Inspection
Planning and Zoning Final Inspection Commercial Electrical Final Inspection
Commercial Building Final
871 Jet Stream Dr
871 Jet Stream Dr - The Rock Gym - New Commercial
Inspection Details
quinton.owens@rexburg.org
Inspected By: Quinton Owens
Building Review on 07/01/2019:
D ESCRIPTIO N CO M M EN TS STATUS
Use classification is identified as per IBC Section
302
Not Identified on plans REVISIONS
504 - Allowable height (Feet/Stories)
506 - Allowable area
Building area actual vs allowed? missing
occupancy type and construction type. Building
area is not identified except on COMcheck and
calculated parking - Is 10,800 exact square
footage or rounded number?
REVISIONS
All buildings shall be classified as one of the five
construction types defined in Section 602.
Not Identified on plans: Combustible materials
(V-A or V-B)
REVISIONS
Fire Resistance Rating of Building Elements
identified in Table 601 meet the requirements of
Section 704.
Construction type?REVISIONS
Occupant load is identified on plans as per IBC
Section 1004
No occupant load identified.REVISIONS
Panic Hardware shall be installed as per IBC
Section 1010.1.10
Panic hardware is required on all egress doors
serving assembly areas.
REVISIONS
Handrails and Guards meet the requirements of
IBC Sections 1014 and 1015
Handrail extensions are not shown at top and
bottom of stairs in the direction of stair run on
both sides (continuous rail in middle is
exception). Allow for 44" minimum egress width
at turn at mezzanine with handrail extension.
REVISIONS
Structural Docs identify snow, wind, seismic and
other loads per IBC Chp. 16
Structural design submitted only for
footing/foundation and mezzanine.
Missing "pre-engineered building manufacturer"
designs.
REVISIONS
Structural Docs or plans identify Risk Category
as per IBC Table 1604.5
Risk Category II (only footing/foundation and
mezzanine plans).
Missing "pre-engineered building manufacturer"
designs.
REVISIONS
Special Inspection Contractor is identified (IBC
1704.2.1)
Who will be performing the special inspections?REVISIONS
Page 1 of 2
(Continued)
Permit Number: 19-00359
D ESCRIPTIO N CO MMEN TS STATUS
Structural Steel has been designed by a licensed
Engineer and meets the requirements of IBC
Chapter 22.
Missing "pre-engineered building manufacturer"
designs.
REVISIONS
Glass and Glazing meets the requirements of IBC
Chapter 24
Tempered glazing is not identified at hazardous
locations.
REVISIONS
Exit Lighting and Exit Signs comply with IBC
1008 & 1013
No lighting plans submitted showing exit signs
and emergency lighting.
REVISIONS
Toilets, Bathing Facilities, Sinks, Kitchens and
Drinking Fountains meet the requirements of IBC
Section 1109
* Women's accessible toilet compartment door
shall not swing into the required minimum area
of the compartment (A117.1, sect 604.9.3).
* Identify location of shower control valves to
show accessibility compliance.
* Other accessible components shall comply
with A117.1 requirements but are not identified.
REVISIONS
Aisles meet the requirements of IBC Section
1018
Assembly areas do not identify any seating
which will be subject to approval at final.
APPROVED
Service Facilities comply with IBC 1109.12 Provide accessible service counter not more
than 36" above floor (30" in length for forward
approach and 36" for parallel approach).
APPROVED
Ventilation is provided as per IBC Section 1203 Required ventilation shall be provided
mechanically.
APPROVED
Page 2 of 2
Inspection
Ticket
Foundation Inspection on 07/01/2019: PART PASS
Permit Number: 19-00359Permit Details
Building - Commercial
Permit Issued Date:
Permit Issued Date: Final Inspections Required
Fire Sprinkler Final Inspection HVAC Final Inspection
Plumbing Final Inspection Fire Department Final Inspection
Public Works Final Inspection Fire Alarm Final Inspection
Planning and Zoning Final Inspection Commercial Electrical Final Inspection
Commercial Building Final
871 Jet Stream Dr
871 Jet Stream Dr - The Rock Gym - New Commercial
Inspection Details
ted.dye@rexburg.org
Inspected By: Ted Dye
Foundation Inspection on 07/01/2019: PART PASS
D ESCRIPTIO N CO M M EN TS STATUS
Forms are plumb and level?COMPLETED
Forms are correct width and in the correct
location?
COMPLETED
Forms are free from debris?COMPLETED
All rebar is tied in place with proper lap?COMPLETED
Rebar is correct size and spaced as per plans?COMPLETED
Rebar is a minimum or 1" from forms?COMPLETED
Foundation walls w/ rebar (city ordinance)COMPLETED
Inspector Comments
Inspected the north wall and the east wall (3/4 of wall).
Inspection
Ticket
Commercial Footing Inspection on 07/01/2019: PASS
Permit Number: 19-00359Permit Details
Building - Commercial
Permit Issued Date:
Permit Issued Date: Final Inspections Required
Fire Sprinkler Final Inspection HVAC Final Inspection
Plumbing Final Inspection Fire Department Final Inspection
Public Works Final Inspection Fire Alarm Final Inspection
Planning and Zoning Final Inspection Commercial Electrical Final Inspection
Commercial Building Final
871 Jet Stream Dr
871 Jet Stream Dr - The Rock Gym - New Commercial
Inspection Details
ted.dye@rexburg.org
Inspected By: Ted Dye
Commercial Footing Inspection on 07/01/2019: PASS
D ESCRIPTIO N CO M M EN TS STATUS
Size and depth are as per plans?COMPLETED
Debris has been removed from inside forms?COMPLETED
All material under forms is properly compacted
and free of frost?
COMPLETED
All rebar is tied in place with proper lap?COMPLETED
Rebar is correct size and is located as per plans?COMPLETED
Rebar is held a minimum of 3" above soil and 2 "
form sides of forms?
COMPLETED
Vertical bar that is to be "stabbed" is present
and has proper bend?
COMPLETED
Building location matches drawings and meets
P&Z setbacks.
COMPLETED
Reber or copper of 20 ft length minimum is
installed and extended above foundation for
attaching and grounding the building's electrical
system. Preferred in footing but may be installed
near bottom of foundation.
COMPLETED
Inspector Comments
6-28-19
Footings set up: completed north side, West side and 1/4 of South side. OK to pour these footings.c
7-1-19
Inspectected the remainder of west footings to complete all footings