HomeMy WebLinkAboutINSPECTION SUMMARY - 14-00295 - 155 W Main #1 - Dominos - RemodelPermit
Inspection
Summary
Permit Status of (Open) as of Report Date: 06/25/2019 9:57 am
Permit Details Permit Number: 14-00295
Dominos - Remodel
155 W Main #1
Commercial Remodel
Permit Issued Date: 07/24/2014
Permit Inspection Statistics
12Total Inspections Completed:
9Total Inspections Passed:
Inspection Pass Rate: 75.00%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
08/15/2014FailTed DyeCommercial Framing/Structure Inspection
Wood studs used in place of steel studs.Inspector Comments:
08/18/2014PassQuinton OwensCommercial Framing/Structure Inspection
Needed backing for HC grab bars in restrooms has been added.Inspector Comments:
08/20/2014PassQuinton OwensCommercial Sheetrock/Drywall Inspection
09/12/2014FailQuinton OwensCommercial Building Final
Grease collector required along back under exhaust filters (keep drain holes
clean). Existing Building remodel items completed.
Inspector Comments:
10/10/2014PassQuinton OwensCommercial Building Final
Grease collector installed.Inspector Comments:
Electrical Inspection Type
08/15/2014PassBret StoddardCommercial Electrical Rough-in
Mechanical Inspection Type
08/14/2014PassQuinton OwensHVAC Rough-in
Existing kitchen hood appears to meet criteria of a type 1 hood (will need to
verify thickness). Old label does not indicate one type or the other. Modifications
will need to be made to meet type 1 hood requirements.
Inspector Comments:
08/20/2014FailDon AllenHVAC Rough-in
need to y in the exhaust fan before they go outInspector Comments:
09/15/2014PassDon AllenHVAC Rough-in
09/15/2014PassDon AllenHVAC Final Inspection
All good for c/oInspector Comments:
Plumbing Inspection Type
08/05/2014PassDon AllenPlumbing Underground Inspection
All good to cover the waist lines.
Still need to look at the grease trap when installed
Inspector Comments:
09/12/2014PassDon AllenPlumbing Final Inspection