Inspection
Summary
Permit Status of (Open) as of Report Date: 05/31/2019 10:24 am
Permit Details Permit Number: 16-00049
450 S Physical Plant Way - BYUI Upper Field Restrooms
450 S Physical Plant Way
Building - Commercial
Permit Issued Date: 05/16/2016
Permit Inspection Statistics
27Total Inspections Completed:
26Total Inspections Passed:
Inspection Pass Rate: 96.30%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
Special inspector on site for pour (submit reports).Inspector Comments:
05/04/2016PassQuinton OwensCommercial Footing Inspection
Ufer not identified in footing (will inspect with foundation).Inspector Comments:
05/05/2016PassQuinton OwensFoundation Inspection
Copper ufer ground in bottom of east foundation wall.Inspector Comments:
05/20/2016PassTed DyeCommercial Footing Inspection
05/25/2016PassQuinton OwensFoundation Inspection
Masonry wall reinforcement at 4'.Inspector Comments:
05/26/2016PassQuinton OwensFoundation Inspection
Masonry wall reinforcement at 8'.Inspector Comments:
05/31/2016PassQuinton OwensFoundation Inspection
Top of exterior masonry wall reinforcement. Special Inspector on site. 2nd
required rebar in top added during inspection.
Inspector Comments:
06/01/2016PassQuinton OwensFoundation Inspection
Interior masonry wall reinforcement at 4'. Special Inspector is on site.Inspector Comments:
06/03/2016PassQuinton OwensFoundation Inspection
Interior masonry wall reinforcement at 8'.Inspector Comments:
Roof framing. Several nails for straps on roof missed blocking. Straps under deck
on north end not completed.
Inspector Comments:
6/28: Reinspected and approved.Inspector Comments:
06/28/2016PassQuinton OwensCommercial Framing/Structure Inspection
Canopy Framing: add missing nails to hangers as indicated in just 3 locations.Inspector Comments:
06/28/2016PassQuinton OwensCommercial Insulation Inspection
Interior foam board insulation.Inspector Comments:
06/30/2016PassQuinton OwensCommercial Framing/Structure Inspection
Approved for drywall .
Add missing insulation on west wall as indicated.
Inspector Comments:
07/05/2016PassQuinton OwensCommercial Sheetrock/Drywall Inspection
07/27/2016PassQuinton OwensSidewalk Inspection
Page 1 of 2
(Continued)
Permit Details Permit Number: 16-00049
450 S Physical Plant Way - BYUI Upper Field Restrooms
450 S Physical Plant Way
Building - Commercial
Permit Status of (Open) as of Report Date: 05/31/2019 10:24 am
Permit
Inspection
Summary
07/28/2016PassQuinton OwensSlab Inspection
Remaining sidewalkInspector Comments:
08/19/2016PassQuinton OwensCommercial Building Final
Electrical Inspection Type
05/17/2016PassBret StoddardElectrical Underground Inspection
05/20/2016PassBret StoddardElectrical Underground Inspection
06/24/2016PassBret StoddardElectrical Rough-in COM-A,R,T
06/30/2016PassBret StoddardElectrical Rough-in COM-A,R,T
08/19/2016FailBret StoddardElectrical Final Inspection COM-A,R,T
08/26/2016PassBret StoddardElectrical Final Inspection COM-A,R,T
Mechanical Inspection Type
06/30/2016PassDon AllenHVAC Rough-in
Good to cover the mechanical rough inInspector Comments:
08/19/2016PassDon AllenHVAC Final Inspection
Good for the c/oInspector Comments:
Plumbing Inspection Type
05/18/2016PassDon AllenPlumbing Underground Inspection
06/30/2016PassDon AllenPlumbing Rough-in
Good to cover the plumbing rough inInspector Comments:
08/19/2016PassDon AllenPlumbing Final Inspection
Good for the c/oInspector Comments: