HomeMy WebLinkAboutINSPECTION SUMMARY - 18-00282 - 172 Charles Place - New SFRPermit
Inspection
Summary
Permit Status of (Issue) as of Report Date: 04/15/2019 3:22 pm
Permit Details Permit Number: 18-00282
172 Charles Place - New SFR
172 Charles Place
Building - Single Family Residence
Permit Issued Date: 01/15/2019
Permit Inspection Statistics
22Total Inspections Completed:
18Total Inspections Passed:
Inspection Pass Rate: 81.82%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
05/29/2018PassLarry BeesleyResidential Footing Inspection
06/07/2018PassLarry BeesleyFoundation Inspection
The foundation forms are set good the re bar is placed correctly in the forms.
You are good to pour the concrete. Thanks
Inspector Comments:
07/03/2018PassDon AllenRadon-Ground Inspection
Radon under ground was ran inside the homeInspector Comments:
09/12/2018PassTed DyeSheeting
All sheeting nailed as per codeInspector Comments:
10/03/2018PassLarry BeesleyResidential Framing/Structure Inspection
You are good to insulate. I am steel going to check the head room on the stairs
to the basement. Thanks, Larry
Inspector Comments:
10/08/2018PARTPASSLarry BeesleyResidential Insulation Inspection
The fire separation on the up stairs truss on the west end needs to be sheet
rocked and inspected before covering any of the ceiling or walls in that area. The
head room on the down stairs basement area needs to be fixed before that is
sheet rocked. Thanks
Inspector Comments:
10/17/2018PassLarry BeesleyCommercial Sheetrock/Drywall Inspection
The sheet rock looks good, You are good to tape. ThanksInspector Comments:
01/15/2019PassLarry BeesleyResidential Insulation Inspection
The insulation is all good and access openings for the attic are in.Inspector Comments:
01/16/2019PassLarry BeesleyResidential Building Final
The house is good for a temporary C.O. There are things that Steve said he
would be getting done in the next two or three days. A temporary railing on the
front step, the back landing and step installed and ladders in the basement
window wells. The garage door is good to enter the house and should be used
until the others are completed. The concrete side walks, drive way , grading and
the landscaping need to be completed by June 1 2019.Also the road needs to be
completed in front of the house. The railing needs to be finished as soon as
possible. Thanks Larry
Inspector Comments:
Page 1 of 2
(Continued)
Permit Details Permit Number: 18-00282
172 Charles Place - New SFR
172 Charles Place
Building - Single Family Residence
Permit Status of (Issue) as of Report Date: 04/15/2019 3:22 pm
Permit
Inspection
Summary
Electrical Inspection Type
08/22/2018PassBret StoddardCOM & MFR Electrical Service Inspection
09/28/2018FailBret StoddardResidential Electrical Rough-in
10/02/2018PassBret StoddardResidential Electrical Rough-in
12/18/2018FailBret StoddardResidential Electrical Final Inspection
01/02/2019FailBret StoddardResidential Electrical Final Inspection
01/11/2019PassBret StoddardResidential Electrical Final Inspection
Mechanical Inspection Type
10/02/2018PassDon AllenHVAC Rough-in
01/15/2019PassDon AllenHVAC Final Inspection
Good for certificate of occupancy on the mechanical systemInspector Comments:
Plumbing Inspection Type
07/02/2018PassDon AllenPlumbing Underground Inspection
07/03/2018PassDon AllenPlumbing Sewer
Good to cove the sewer line.Inspector Comments:
09/14/2018PassDon AllenPlumbing Rough-in
01/15/2019PassDon AllenPlumbing Final Inspection
01/15/2019PassDon AllenPlumbing Water
Water is good to cover. The water meter is under snow and cannot get a pictureInspector Comments:
Page 2 of 2