Permit Status of (Open) as of Report Date: 04/15/2019 2:40 pm
Permit Details Permit Number: 18-00260
155 W 2nd S Suite 180 - Five Guys Burgers and Fries - Tenant Finish
155 W 2nd S Suite 180
Commercial Tenant Finish
Permit Issued Date: 06/18/2018
Permit Inspection Statistics
32Total Inspections Completed:
13Total Inspections Passed:
Inspection Pass Rate: 40.63%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
06/22/2018PARTPASSTed DyeCommercial Insulation Inspection
Steel framed walls only.
* Rated walls need penetrations rated (plastic pipe over 3" will require a fire
collar).
* Finish taping joints in drywall on fire rated wall.
* Clean outs in rated walls also require fire rated protection
* Fire block penetrations through concrete slab above.
* Reinforcement for grab bars needs to be added for all 4 restrooms.
Inspector Comments:
07/03/2018FailQuinton OwensCommercial Framing/Structure Inspection
Water heater platform framing also inspected as requested and approved.Inspector Comments:
Call Scott with a time. AM. 801-628-4945Inspector Comments:
07/13/2018PARTPASSQuinton OwensCommercial Sheetrock/Drywall Inspection
cement board inspection around cooking appliances only. Approved to cover.Inspector Comments:
07/16/2018PARTPASSTed DyeCommercial Framing/Structure Inspection
Call to schedule time *951-479-6893*Inspector Comments:
07/18/2018PassTed DyeCommercial Sheetrock/Drywall Inspection
Call when you're on your way. Any time AM.Inspector Comments:
08/24/2018PassTed DyeSuspending Ceiling Inspection
08/31/2018FailTed DyeCommercial Building Final
09/04/2018FailTed DyeCommercial Building Final
02/06/2019PassQuinton OwensCommercial Building Final
Electrical Inspection Type
07/02/2018PARTPASSBret StoddardCommercial Electrical Rough-in
07/17/2018PARTPASSBret StoddardCommercial Electrical Rough-in
08/27/2018PassBret StoddardCommercial Electrical Rough-in
09/05/2018PassBret StoddardCommercial Electrical Final Inspection
Page 1 of 4
(Continued)
Permit Details Permit Number: 18-00260
155 W 2nd S Suite 180 - Five Guys Burgers and Fries - Tenant Finish
155 W 2nd S Suite 180
Commercial Tenant Finish
Permit Status of (Open) as of Report Date: 04/15/2019 2:40 pm
Permit
Inspection
Summary
Fire Inspection Type
08/28/2018PassDavid DavisFire Sprinkler Rough-in
Needs one lateral bracing in hallway area. Alma said he would do that and have
ready to the final. He was also going to hydro the system again, now that they
are finished with this part of the building.
Inspector Comments:
08/30/2018PassDale PickeringFire Department Final Inspection
08/30/2018PassDavid DavisFire Sprinkler Rough-in
08/30/2018PassDavid DavisFire Sprinkler Final Inspection
Page 2 of 4
(Continued)
Permit Details Permit Number: 18-00260
155 W 2nd S Suite 180 - Five Guys Burgers and Fries - Tenant Finish
155 W 2nd S Suite 180
Commercial Tenant Finish
Permit Status of (Open) as of Report Date: 04/15/2019 2:40 pm
Permit
Inspection
Summary
Mechanical Inspection Type
Call Scott at 801-628-4945 with inspection time. He requested an AM inspection.Inspector Comments:
08/01/2018FailDon AllenHVAC Rough-in
Need to finish rough inInspector Comments:
08/03/2018PARTPASSDon AllenHVAC Rough-in
Remainder of grease duct at main level (above kitchen area) inspected for light
test. Welds look complete - no holes found.
* GREASE DUCT CLEANOUT will be required for per IMC 506.3.8 and 506.3.9.
Inspector Comments:
08/09/2018PARTPASSQuinton OwensHVAC Rough-in
Inspected supply and return duct for Five Guys in common shaft at 3rd & 4th
level.
* Duct is good up to unfinished last connection through roof.
* Fire rating for ceiling of shaft will need to be completed before enclosing shaft
(building code requirement).
Inspector Comments:
08/28/2018FailQuinton OwensHVAC Rough-in
Re-inspection needed on grease ducts.
* Grease Duct final inspection: Access doors still to be installed; Duct wrap is not
continuous going into shaft due to drywall and fire caulk against shaft (bottom of
shaft does not have to be sealed off - the whole shaft is rated to roof).
* HVAC duct re-inspection: ducts sealed and supported over kitchen and
restrooms (approved)
Inspector Comments:
Inspected grease duct access openings above kitchen hood. Performed light test
on welded patch. Approved to cover grease duct above kitchen hood.
Inspector Comments:
08/30/2018PARTPASSQuinton OwensHVAC Rough-in
Other grease duct access doors will be inspected after welded patches are done.Inspector Comments:
08/31/2018FailQuinton OwensHVAC Final Inspection
8/31/18: NOT READY for re-inspection of grease duct access openings and
removal of drywall against grease duct and continuous wrap at entry into shaft.
Inspector Comments:
09/04/2018FailDon AllenHVAC Final Inspection
09/06/2018PassDon AllenHVAC Final Inspection
09/20/2018FailDon AllenHVAC Final Inspection
Still need to finish up the ducting on the roof.Inspector Comments:
09/25/2018PARTPASSDon AllenHVAC Final Inspection
Need to support ductwork that is installed on the roofInspector Comments:
10/16/2018FailDon AllenHVAC Final Inspection
10/19/2018PassDon AllenHVAC Final Inspection
Page 3 of 4
(Continued)
Permit Details Permit Number: 18-00260
155 W 2nd S Suite 180 - Five Guys Burgers and Fries - Tenant Finish
155 W 2nd S Suite 180
Commercial Tenant Finish
Permit Status of (Open) as of Report Date: 04/15/2019 2:40 pm
Permit
Inspection
Summary
Plumbing Inspection Type
06/29/2018PassDon AllenPlumbing Underground Inspection
Good to cover Plumbing underground in Five GuysInspector Comments:
07/11/2018PARTPASSDon AllenPlumbing Rough-in
Good to cover the interior walls. Will need to see the water lines and vent lines
before ceiling is installed
Inspector Comments:
09/04/2018PassDon AllenPlumbing Final Inspection