HomeMy WebLinkAboutINSPECTION SUMMARY - 17-00309 - 525 S Center St - BYUI - Austin Bldg RemodelPermit
Inspection
Summary
Permit Status of (Issue) as of Report Date: 04/03/2019 12:27 pm
Permit Details Permit Number: 17-00309
BYUI - Austin Bldg Remodel
525 S Center St
Commercial Remodel
Permit Issued Date: 08/02/2017
Permit Inspection Statistics
28Total Inspections Completed:
15Total Inspections Passed:
Inspection Pass Rate: 53.57%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
10/24/2017PassTed DyeCommercial Framing/Structure Inspection
Steel stud construction. All joints have the proper connection(screwed to gether).Inspector Comments:
10/30/2017PassTed DyeCommercial Sheetrock/Drywall Inspection
12/11/2017PassQuinton OwensSuspending Ceiling Inspection
HVAC ducts still to be connected and inspected.
Fireproofing to be patched in various locations.
One light by retracting wall motor still needs seismic ties.
Ceiling grid installation is approved.
Inspector Comments:
01/04/2018PassTed DyeCommercial Building Final
04/26/2018PassTed DyeCommercial Footing Inspection
05/30/2018PARTPASSQuinton OwensCommercial Building Final
Accessible restrooms only inspected and approved on north end of main level.Inspector Comments:
Electrical Inspection Type
09/07/2017PARTPASSBret StoddardCommerical Electrical Final Inspection
10/20/2017PARTPASSBret StoddardCommercial Electrical Rough-in
12/08/2017PARTPASSBret StoddardCommercial Electrical Rough-in
01/04/2018PARTPASSBret StoddardCommerical Electrical Final Inspection
02/05/2018PARTPASSBret StoddardElectrical Underground Inspection
02/08/2018PARTPASSBret StoddardCommercial Electrical Rough-in
03/07/2018PARTPASSBret StoddardCommercial Electrical Rough-in
04/17/2018PARTPASSBret StoddardCommerical Electrical Final Inspection
09/06/2018PassBret StoddardCommercial Electrical Final Inspection
Page 1 of 2
(Continued)
Permit Details Permit Number: 17-00309
BYUI - Austin Bldg Remodel
525 S Center St
Commercial Remodel
Permit Status of (Issue) as of Report Date: 04/03/2019 12:27 pm
Permit
Inspection
Summary
Fire Inspection Type
09/08/2017PassDale PickeringFire Sprinkler Hydro
09/08/2017PassDale PickeringFire Sprinkler Rough-in
01/04/2018PARTPASSBret StoddardFire Alarm Final Inspection
04/18/2018PARTPASSBret StoddardFire Alarm Final Inspection
02/25/2019PassBret StoddardFire Alarm Final Inspection
Mechanical Inspection Type
01/04/2018PARTPASSDon AllenHVAC Final Inspection
Need the air test for the duct system in the welding lab room 170. in rooms 221
213 204 202 202a 204 206 208 210 and 212 are good to hold classes in.
Inspector Comments:
02/25/2019PassDon AllenHVAC Final Inspection
Plumbing Inspection Type
10/17/2017PassDon AllenPlumbing Rough-in
good to cover the sinksInspector Comments:
01/04/2018PassDon AllenPlumbing Final Inspection
The 2 sinks that where installed in room 202 was done to code.Inspector Comments:
01/24/2018PassDon AllenPlumbing Underground Inspection
Good to cover the plumbing underground in the basement of the buildingInspector Comments:
02/07/2018PassDon AllenPlumbing Rough-in
05/30/2018PARTPASSDon AllenPlumbing Final Inspection
02/25/2019PassDon AllenPlumbing Final Inspection
Page 2 of 2