HomeMy WebLinkAboutCollections SCADA Rev2
Proposal
October 19, 2018
Justin Beard
City of Rexburg
Re: Collections SCADA System – Revisions Based on meeting held 3/26/19
Mr. Beard,
SKM is pleased to provide this proposal to provide SCADA hardware and programming for the City of
Rexburg wastewater collections system. The scope of this proposal was derived from information provided
by the city and site visits on October 18th, 2018.
Scope of Services
1. Task 1 – Communications System
a. Provide Radwin radio hardware for a communications system based at the city water
tower. This system would utilize the 4.9 GHz range.
b. Commission radios at each location to determine exact locations of antennas/radios.
2. Task 2 – Lift Station Panels – This includes providing a PLC panel for each lift station to control
two pumps and monitor wet well conditions as well as a generator if generator is present. Each
panel will be integrated back to the main SCADA server. Each panel will be a NEMA 12 box rated
for outdoor installation with the exception of the Main Lift Station. We are planning on providing
panels at the following locations:
a. Airport Lift Station
b. Main Lift Station
c. Summerfield Lift Station
d. 12th West Lift Station
e. 7th South Lift Station
f. University Blvd Lift Station
g. Yellowstone Lift Station
h. Sunrise Lift Station
i. Syringa Lift Station
j. Valley River Lift Station
k. East Moody Lift Station
l. Larch Lift Station
3. Task 3 – Job Records and Bid Support
a. Provide bid documents for electricians on the install
b. Provide O&M manual for the system
c. Provide record panel drawings
4. Task 4 – Storm Water Lift Station I/O Panel
a. 7th South Stormwater Lift Station
5. Task 5 – Lift Station SCADA
a. Site programming and set-up within Ignition
6. Task 6 - Intrinsic Barrier
a. Provide an intrinsically safe junction box for the wastewater lift stations. The ones we
visited had no intrinsic protection
7. Task 7 – Backup Floats
a. Provide a level float for each wastewater lift station to function as a back-up
8. Task 8 –Recommended Spare Parts
a. This would include the following spare parts. We recommend the following spare parts
for the project.
i. Spare base station radio
ii. Spare remote
iii. Spare PLC
iv. Spare IO card of each type and power supply
Responsibility of Others
The following services will be provided by others:
1. Installation of the hardware on site. Hardware will be shipped to site to be installed by an electrical
contractor.
Cost Proposal
Our fees for the above listed scope of services will be provided on a time and materials basis not to exceed
the total fee shown below. Additional reimbursable expenses will be charged at cost plus 10% markup. This
proposal will be valid for the next 60 days.
Project Costs
Task 1 Communications System $12,400 1 $12,400
Task 2 PLC Panels $9,600 12 $115,200
Task 3 Job Records $8,500 1 $8,500
Task 4 Storm Water Stations – IO $8,300 1 $8,300
Task 5 Lift Station SCADA Programming $20,000 1 $20,000
Task 6 Intrinsic Barrier Boxes $1,100 12 $13,200
Task 7 Backup Floats $60 12 $720
Task 8 Spare Parts $8,200 1 $8,200
Project Total $186,520
Standard Hourly Rates
Project Manager $125
Designer / Technician $115
Expenses Billed at cost + 10% markup
Confidentiality
The Client agrees that the technical methods, techniques and pricing information contained in any proposal
submitted by SKM pertaining to this project or in this Agreement or any addendum thereto, are to be
considered confidential and proprietary, and shall not be released or otherwise made available to any third
party without the express written consent of SKM.
Best Regards,
Allen Rogers
SKM
Accepted by
Signature Printed Name
Title Date
Attached: Articles of Terms and Conditions