Permit Status of (Issue) as of Report Date: 02/05/2019 4:23 pm
Permit Details Permit Number: 17-00448
Homestead Bldg 3 - Addition
407 W 1st N
Commercial Addition
Permit Issued Date: 11/20/2017
Permit Inspection Statistics
58Total Inspections Completed:
33Total Inspections Passed:
Inspection Pass Rate: 56.90%
Permit Inspection History *Refer to Individual Inspection Report for more Details
08/08/2018PassQuinton OwensPlanning and Zoning Final Inspection
Site work appears to be completed as per plans and review comments for
Planning & Zoning requirements.
Inspector Comments:
01/04/2019PassJoel GrayPublic Works Final Inspection
Building Inspection Type
09/18/2017PassTed DyeCommercial Footing Inspection
09/19/2017PassTed DyeFoundation Inspection
Ufer grounds are located in south east corner of foundation on both sides of the
door.
Inspector Comments:
09/28/2017PassLarry BeesleyCommercial Insulation Inspection
The insulation is installed and OK to back fill against.Inspector Comments:
10/17/2017PassTed DyeCommercial Footing Inspection
Shovel footings under slabInspector Comments:
11/30/2017PARTPASSTed DyeCommercial Sheetrock/Drywall Inspection
Fire separation wall between the old and the new buildings.Inside wall had 2
layers of 5/8" Type X drywall, fire taped.
Inspector Comments:
02/28/2018PARTPASSTed DyeCommercial Sheetrock/Drywall Inspection
Pre-rock behind shower.
Discussed the separation wall and how to reach the 1hr rating that is
required,also the 2hr wall at the riser room.
Inspector Comments:
03/26/2018PARTPASSQuinton OwensCommercial Sheetrock/Drywall Inspection
APPROVED FOR INSULATION (pending rough inspections approved for insulating)Inspector Comments:
03/30/2018FailQuinton OwensCommercial Framing/Structure Inspection
Electrical boxes on opposite sides of a fire partition and in the same stud cavity
need to be separated by fire blocking or distance required by manufacturer.
Inspector Comments:
04/02/2018FailTed DyeCommercial Framing/Structure Inspection
04/03/2018PassTed DyeCommercial Framing/Structure Inspection
04/09/2018PassTed DyeCommercial Insulation Inspection
Page 1 of 4
(Continued)
Permit Details Permit Number: 17-00448
Homestead Bldg 3 - Addition
407 W 1st N
Commercial Addition
Permit Status of (Issue) as of Report Date: 02/05/2019 4:23 pm
Permit
Inspection
Summary
04/13/2018PARTPASSTed DyeCommercial Sheetrock/Drywall Inspection
Units approved: 105-108 and 126-129Inspector Comments:
04/16/2018PARTPASSTed DyeCommercial Sheetrock/Drywall Inspection
additional units inspected; 109, 124 and 125
Previous inspected units 4-13-18 were 105 through 108 and 126 through 129.
Inspector Comments:
04/20/2018PassTed DyeCommercial Sheetrock/Drywall Inspection
04/25/2018PARTPASSTed DyeCommercial Sheetrock/Drywall Inspection
Locations inspected; Halls and Janitors roomInspector Comments:
04/30/2018PassTed DyeCommercial Building Final
Kitchen inspection only. Includes the 2 new coolers and beverage dispenser area.Inspector Comments:
05/09/2018PassTed DyeCommercial Footing Inspection
the inspection was for a approach on east side of building.
Rebar at 18" in both directions.
Depth of concrete was 6 Plus
Inspector Comments:
05/09/2018PassTed DyeCommercial Sheetrock/Drywall Inspection
Main assembly room.
All but a few area's that have not been done.
Pictures attached
Inspector Comments:
05/15/2018PassTed DyeCommercial Sheetrock/Drywall Inspection
All the drywall has been copmpleted in the main gathering area to complete
building.
Inspector Comments:
06/08/2018PARTPASSTed DyeCommercial Sheetrock/Drywall Inspection
Talk to contractor about fire sealant on walls.Inspector Comments:
06/13/2018PassTed DyeCommercial Sheetrock/Drywall Inspection
* exterior landing at door to storage closet on west side of addition will be
allowed to have a step up to threshold based on an exception in 1003.5.
* Landing to have no more than 2% slope.
Inspector Comments:
* Sidewalk at east entrance door of addition and at the handicap parking access
may not exceed 8% slope as a ramp with 2% maximum cross slope and will not
require a handrail where it does not exceed 6 inches of rise.
* Landing is required at threshold of building entrance and at sidewalk
intersections.
Inspector Comments:
07/18/2018PARTPASSQuinton OwensSlab Inspection
This inspection was to address questions before pouring concrete and will be
inspected for approval when done. Rebar also installed in driveway replacement
by existing building.
Inspector Comments:
07/26/2018FailTed DyeCommercial Building Final
Notice additional findings that need to be addressed.Inspector Comments:
Page 2 of 4
(Continued)
Permit Details Permit Number: 17-00448
Homestead Bldg 3 - Addition
407 W 1st N
Commercial Addition
Permit Status of (Issue) as of Report Date: 02/05/2019 4:23 pm
Permit
Inspection
Summary
08/07/2018PassJoel GrayFoundation Inspection
;The foundation insection was done prier to this entry.
For some reason it is not showing up in the inspection entry.
Inspector Comments:
08/07/2018PassTed DyeCommercial Building Final
08/09/2018PassTed DyeCommercial Building Final
Electrical Inspection Type
03/26/2018PARTPASSBret StoddardCommercial Electrical Rough-in
03/30/2018PassBret StoddardCommercial Electrical Rough-in
04/03/2018PassBret StoddardCommercial Electrical Rough-in
04/23/2018N/ABret StoddardCommerical Electrical Final Inspection
04/25/2018FailBret StoddardCommercial Electrical Final Inspection
04/26/2018PARTPASSBret StoddardCommercial Electrical Final Inspection
07/30/2018FailBret StoddardCommercial Electrical Final Inspection
08/07/2018PassBret StoddardCommercial Electrical Final Inspection
Fire Inspection Type
03/30/2018FailBret StoddardFire Alarm Rough-in
04/02/2018PassBret StoddardFire Alarm Rough-in
04/24/2018PassDale PickeringFire Sprinkler Rough-in
04/30/2018PassDale PickeringFire Sprinkler Rough-in
04/30/2018PassDale PickeringFire Department Final Inspection
06/20/2018PARTPASSDavid DavisFire Sprinkler Final Inspection
System is up and running but needs a finished door on riser room and signage on
the door
Inspector Comments:
07/30/2018PassBret StoddardFire Alarm Final Inspection
08/07/2018PassDale PickeringFire Sprinkler Final Inspection
Page 3 of 4
(Continued)
Permit Details Permit Number: 17-00448
Homestead Bldg 3 - Addition
407 W 1st N
Commercial Addition
Permit Status of (Issue) as of Report Date: 02/05/2019 4:23 pm
Permit
Inspection
Summary
Mechanical Inspection Type
03/29/2018FailDon AllenHVAC Rough-in
Missing seal on parts of the duct work. call when sealed up.Inspector Comments:
04/02/2018PassDon AllenHVAC Rough-in
04/23/2018FailDon AllenHVAC Final Inspection
04/25/2018PARTPASSDon AllenHVAC Final Inspection
07/31/2018PARTPASSDon AllenHVAC Final Inspection
08/07/2018PassDon AllenHVAC Final Inspection
Plumbing Inspection Type
10/11/2017PassDon AllenPlumbing Underground Inspection
Good to cover the plumbing undergroundInspector Comments:
03/23/2018PassDon AllenPlumbing Rough-in
03/29/2018PassDon AllenPlumbing Rough-in
need to finish rough in. Call when finished.Inspector Comments:
04/02/2018PassDon AllenPlumbing Rough-in
04/23/2018FailDon AllenPlumbing Final Inspection
04/25/2018PARTPASSDon AllenPlumbing Final Inspection
07/31/2018PARTPASSDon AllenPlumbing Final Inspection
08/07/2018PassDon AllenPlumbing Final Inspection