HomeMy WebLinkAboutTEMP CO - 18-00244 - 17 S 4th W - Snellgrove Townhomes - #402Certificate of Occupancy
City of Rexburg
Department of Community Development
35 N. 1st E. / Rexburg, ID. 83440
Phone (208) 359-3020 / Fax (208) 359-3022
Building Permit Number
Site Address
18-00244
17 S 4th W
Description of Building or
Portion of Building covered by Certificate
Snellgrove Townhomes - #402
Woodshed Properties LLC
342 W 1st S, ID 83440
Name and Address of Owner
Contractor KDS Developing LLC
Applicable Edition of Code IRC 2012
Construction Type VB
R-3 Residential - One and two family homes
680 sq ft - Square footage - Unfinished basement
1,380 sq ft - Square footage - Main and upper Levels
680 sq ft - Square footage - Unfinished basement
Use and Occupancy (sq. ft.)
Design Occupant Load N/A
Sprinkler System Required?No
Sprinkler System Provided?No
Special Conditions The individual spaces need to marked with cones to keep construction workers from
parking there. When work on the North building starts you need to have candles with
rope to separate construction traffic from residence. Parking lot needs to be paved along
with the sidewalks and curbing on 4th West by May 30th 2019. Carports need to be built
after pavement is placed. Grading of the dirt and landscaping need to be completed in
early spring. Well need to look at water meter for final grade will also need to make sure
that the main clean out for the sewer line has the clearance necessary.
This Certificate, issued pursuant to the requirements of Section 111 of the International Building Code,
certifies that, at the time of issuance, this building or that portion of the building that was inspected on the
date listed was found to be in compliance with the requirements of the code for the group and division of
occupancy and the use for which the proposed occupancy was classified.
Date C.O. Issued
Building Official:Public Works:
There shall be no further change in the existing occupancy classification of the building nor shall any
structural changes, modifications or additions be made to the building or any portion thereof until the
Building Official has reviewed and approved said future changes.
January 28, 2019