Permit Status of (Issue) as of Report Date: 12/06/2018 1:52 pm
Permit Details Permit Number: 17-00266
930 Hillview - SFR Addition and Spa
930 Hillview
Single Family Residential Addition
Permit Issued Date: 05/23/2017
Permit Inspection Statistics
10Total Inspections Completed:
8Total Inspections Passed:
Inspection Pass Rate: 80.00%
Permit Inspection History *Refer to Individual Inspection Report for more Details
Building Inspection Type
07/17/2017FailLarry BeesleyResidential Framing/Structure Inspection
The windows are considered a hazardous location as per code R.308.4.5 and
R.308.4.6 The glass needs to be tempered, because they are closer than 60
inches to the edge of the hot tub or waters edge. 7-14-17
Inspector Comments:
11/09/2017FailLarry BeesleyResidential Building Final
02/08/2018PassLarry BeesleyResidential Framing/Structure Inspection
12/05/2018PassLarry BeesleyResidential Insulation Inspection
12/06/2018PassLarry BeesleyResidential Footing Inspection
I talked with Ted Dye about the Inspection for the footings. I also called Terry
Leishman about the size and amount of rebar that was put in the footings. It
was 2 bars of 1/2" re bar and verticals every 2' on center. This is good and meets
the code. There is no insulation or blue board under the floor or inside of the
foundation. The inspection wasn't called in to the hot line at the time.
Inspector Comments:
12/06/2018PassLarry BeesleyFoundation Inspection
The foundation inspection was not completed at the time is was set and poured.
I called Terry Leishman, The builder and the told me that it had 1/2' rebar on 2'
centers and built as per the code.
Inspector Comments:
12/06/2018PassLarry BeesleySheeting
The sheeting inspection was done by me at the time of the first framing
inspection and it was all good.
Inspector Comments:
12/06/2018PassLarry BeesleyResidential Building Final
I talked with Terry Leishman, and went over the areas that haden't been
inspected, and with the information he gave me I was able to sign off on the
Insulation, footings and foundation. The other corrections were changing the
windows to Tempered glass. This has been completed and there is a hand rail for
the steps. This should complete this project and be final-ed. Thanks, Larry
Inspector Comments:
Electrical Inspection Type
07/17/2017PassBret StoddardResidential Electrical Rough-in
11/08/2017PassBret StoddardResidential Electrical Final Inspection