HomeMy WebLinkAboutPLUMBING REVIEW SUMMARY - 18-00285 - 2300 University Blvd - Madison High School Stadium - New ConstructionReview
Report
Current Plumbing Review Status: RESUBMIT
Application Number: 18-00285Permit Details
Application Received Date: 05/29/2018
Commercial Addition
Application Approved Date:
Application Approved Status: ACPTW/COND
05/29/2018
2300 University Blvd
Madison High School Stadium - New Construction
Status of Plan Reviews Completed
05/29/2018Electrical Review N/A
05/31/2018Public Works Review - Site Plan REVISIONS
06/05/2018Fire Department Review - Site Plan COMPLETED
06/06/2018Planning and Zoning Review - Site Plan REVISIONS
07/31/2018Plumbing Review RESUBMIT
07/31/2018HVAC Review COMPLETED
07/31/2018Electrical Review REVISIONS
08/01/2018Planning and Zoning Review - Site Plan REVISIONS
08/01/2018Public Works Review - Site Plan REVISIONS
08/02/2018Building Review REVISIONS
08/08/2018Planning and Zoning Review - Site Plan APPW/COND
Permit Review Status
Plan Reviews Still in Progress
Public Works Review - Site Plan
Electrical Review
Public Works Review - Site Plan
Building Review
DESCRIPTION COMMENTS STA TUS
*Please respond to "REVISIONS" status items, with appropriate comment/documentation as needed!
Meter Size/ Wye Strainer REVISIONS Need to know the water meter size for the
building.
*Revisions Response :
Reviewed By: Don Allen
Review Date: 07/31/2018
Plan Review Details
don.allen@rexburg.org
Plumbing Review Status: RESUBMIT
Additional Inspector Comments:
Need to install a grease test manhole on the down stream of the grease interceptor
Need to install all mechanical to the 2015 IMC.
Grease interceptor is good to go per Don.
Page 1 of 1
Approval of plans does not constitue approval of variance from code
Review
Report
Current HVAC Review Status: APPROVED
Application Number: 18-00285Permit Details
Application Received Date: 05/29/2018
Commercial Addition
Application Approved Date:
Application Approved Status: ACPTW/COND
05/29/2018
2300 University Blvd
Madison High School Stadium - New Construction
Status of Plan Reviews Completed
05/29/2018Electrical Review N/A
05/31/2018Public Works Review - Site Plan REVISIONS
06/05/2018Fire Department Review - Site Plan COMPLETED
06/06/2018Planning and Zoning Review - Site Plan REVISIONS
07/31/2018Plumbing Review RESUBMIT
07/31/2018HVAC Review COMPLETED
07/31/2018Electrical Review REVISIONS
08/01/2018Planning and Zoning Review - Site Plan REVISIONS
08/01/2018Public Works Review - Site Plan REVISIONS
08/02/2018Building Review REVISIONS
08/08/2018Planning and Zoning Review - Site Plan APPW/COND
Permit Review Status
Plan Reviews Still in Progress
Public Works Review - Site Plan
Electrical Review
Public Works Review - Site Plan
Building Review
Reviewed By: Don Allen
Review Date: 07/31/2018
Plan Review Details
don.allen@rexburg.org
HVAC Review Status: APPROVED
Additional Inspector Comments:
Need to install a grease test manhole on the down stream of the grease interceptor
Need to install all mechanical to the 2015 IMC.
Grease interceptor is good to go per Don.
Page 1 of 1
Approval of plans does not constitue approval of variance from code