HomeMy WebLinkAboutINSPECTION TICKET 2 - 18-00386 - 485 N 2nd E - Mongolian Restaurant - RemodelInspection
Ticket
Commercial Building Final on 10/05/2018: FAIL
Permit Number: 18-00386Permit Details
Commercial Remodel
Permit Issued Date: 08/03/2018
Final Inspections Required
Commercial Electrical Final Inspection HVAC Final Inspection
Commercial Building Final
485 N 2nd E
Mongolian Restaurant - Remodel
Inspection Details
quinton.owens@rexburg.org
Inspected By: Quinton Owens
Commercial Building Final on 10/05/2018: FAIL
D ESCRIPTIO N CO M M EN TS STATUS
Mechanical, Electrical, Plumbing are required as
well as P&Z, Public Works, Fire Dept. and Fire
Sprinklers where sprinkler system exists.
All finals require approval for occupancy.
Inspections still to be entered as completed are
Fire Dept, Electrical, HVAC, Plumbing, and
address approval. Addresses 103A and 103B are
not in the GIS system and were put into review
for approval (follow up will be done on
Monday).
FAIL
Exit signs are located properly.Exit sign is missing by east end of back corridor
(to be visible from majority of dining area).
FAIL
Occupant load is posted as required.Post occupant load in conspicuous place near
main entrance. Sign to be of a permanent
nature and easily legible.
FAIL
Restrooms meet accessibility standard.* Existing restrooms approved without vertical
grab bar because it was built prior to its
requirement and no backing is provided.
* Finish installing dispensers in restrooms so
operable parts are not more than 48" above
floor. Seal water line penetration in wall behind
toilet.
COMPLETED
Inspector Comments
Tables and chairs are not set up yet, but may be checked for aisle and aisle access requirements when done.