Current Public Works Review - Site Plan Status: REVISIONS
Application Number: 18-00175Permit Details
Application Received Date: 04/04/2018
Multi-Family Residential
Application Approved Date:
Application Approved Status: ACCEPTED
04/04/2018
220 S 2nd W
Arbor Cove - Bldg #1 - 34 Units - New Dormitory Housing
Status of Plan Reviews Completed
04/06/2018Fire Department Review - Site Plan COMPLETED
04/16/2018Planning and Zoning Review - Site Plan REVISIONS
04/18/2018Public Works Review - Site Plan REVISIONS
05/14/2018Building Review REVISIONS
06/07/2018Electrical Review COMPLETED
06/11/2018Plumbing Review COMPLETED
06/11/2018HVAC Review COMPLETED
06/27/2018Building Review REVISIONS
Permit Review Status
Plan Reviews Still in Progress
Planning and Zoning Review - Site Plan
Public Works Review - Site Plan
Building Review
DESCRIPTION COMMENTS STA TUS
*Please respond to "REVISIONS" status items, with appropriate comment/documentation as needed!
Plans are approved for a footing/foundation
ONLY permit?
YES
Checked for linked cases YES
Sewer: Line size/slope/type materials REVISIONS12" line needs to continue to 1st S with uniform
grade between 1st and 2nd S.
DEQ Approval required.
*Revisions Response :
Miscellaneous Review REVISIONSWhat is being done for pedestrian lighting in
right of way?
*Revisions Response :
Miscellaneous Review REVISIONSFire Hydrants require storz adapter.
*Revisions Response :
Miscellaneous REVISIONSTraffic impact study and development
agreement may require additional items.
*Revisions Response :
Reviewed By: Joel Gray
Review Date: 04/18/2018
Plan Review Details
joel.gray@rexburg.org
Public Works Review - Site Plan Status: REVISIONS
Page 1 of 2
Approval of plans does not constitue approval of variance from code
Public Works Review - Site Plan (Continued)
D ESCRIPTIO N CO MMEN TS STATUS
Miscellaneous N/ATrash enclosure dimension of 32' is inside not
outside dimension.
Site Lighting : Photometric layout N/ANo site Lighting on plans.
Parking Lot : Drainage COMPLETED
Parking Lot: Accessibility/layout COMPLETED
Street : Sidewalk setback/continuos Must connect to existing sidewalk at each end.COMPLETED
Street : Curb type COMPLETED
Street : Entrance placement COMPLETED
Sewer: Manhole placement COMPLETED
Sewer: Connection to mainline COMPLETED
Water : Connection to main line COMPLETED
Water : Valve placement COMPLETED
Storm : Drainage calcs COMPLETED
Storm : On-site retention Suggest elbow inside manhole prior to piping to
storage area.
COMPLETED
Storm : Infiltrators COMPLETED
Page 2 of 2
Approval of plans does not constitue approval of variance from code