Final Budget
2017 2018
Fund Balance as of beginning of year 4,065,746$ 4,353,533$
Less Set Aside-Investment Set Aside-Finance Software (135,700)$ (175,700)$
Actual/Forecast/Budgeted Carryover(shortage)423,487$ (207,500)$
Net as of end of the year 4,353,533$ 3,970,333$
Expenditures including contingency 10,593,292$ 11,727,800$
Less Contingency n/a (136,000)$
Net Expenditures 10,593,292$ 11,591,800$
Minimum Reserve % of Expenditures:25%2,648,323$ 2,897,950$
Amount Above Minimum Reserve:25%1,705,210$ 1,072,383$
Actual Percentage 41.10%34.25%
Maximum Reserve % of Expenditures 33%3,495,786$ 3,825,294$
Amount over/(Under) 33%857,747$ 145,039$
2018 2019
General Fund Transfers-Subsidies Forecast Budget
FUND TFR -GOLF OPERATIONS 49,700 39,100
FUND TFR - TRAILS FUND 25,000
FUND TFR - VETERANS MEMORIAL TRUST FUND 500
FUND TFR -LEGACY FLIGHT MUSEUM 10,500 10,500
FUND TFR -AIRPORT CONSTRUCTION 10,000 10,000
FUND TFR -POLICE IMPACT FEE FD 0 0
FUND TFR -PLANNING & ZONING 293,600 315,000
FUND TFR -REXBURG CULTURAL ART 31,900 34,700
FUND TFR -E I BUSINESS COMP 7,000 6,000
FUND TFR -MAYOR'S YOUTH ADV BD 3,500 1,500
FUND TFR-GOLF CON.LOAN PAYBACK 20,000 25,000
FUND TFR- AIRPORT OPERATIONS 2,000 2,000
FUND TFR -ROMANCE/FUND 30 74,500 181,200
FUND TFR -DARE/FUND 09 FOR DEF 8,500 8,500
FUND TFR -RECREATION 83,000 99,500
FUND TFR -TABERNACLE 191,800 153,000
FUND TFR -JOINT FIRE EQUIP 35,000 35,000
FUND TFR AIRPORT RELOC.RESERVE 169,400 100,000
FUND TFR -ANIMAL CONTROL FUND 159,200 186,700
FUND TFR -REXBURG ORCHESTRA 7,500 5,000
FUND TFR -JOINT FIRE OPERATION 997,300 1,150,000
FUND TFR -R RAPIDS CAP REPLACE 65,000 60,000
2,219,400$ 2,448,200$
Street Funds
Fund Description Fund
2018
Forecasted
Carryover
2019
Budgeted
Carryover
Accounts
Receivable
5/23/18 Notes
Street Operations 2 -$ -$ 52,000$
Street Impact 33 1,194,200$ 999,200$
Street Repair 43 1,302,500$ 1,280,600$ 428,896$
New Street Construction 44 -$ -$ -$
Total 2,496,700$ 2,279,800$ 480,896$
Total Available Cash/Investments 2,015,804$
Sanitation Fund 2018 2019
Fund Description Fund
Year End
Forecasted
Reserve*
Year End
Budgeted
Reserve*Notes
Sanitation Operations 25 856,857$ 496,657$
Water Funds 2018 2019
Fund Description Fund
Year End
Forecasted
Reserve*
Year End
Budgeted
Reserve*Notes
Water Operations 26 6,729,032$ 6,371,032$
Water Capital Reserve 34 1,756,000$ 1,631,300$
Water Capital Construction 42 -$
Water Line Extension 46 -$
Total 8,485,032$ 8,002,332$
Wastewater Funds 2018 2019
Fund Description Fund
Year End
Forecasted
Reserve*
Year End
Budgeted
Reserve*Notes
Sewer Operations 27 2,888,737$ 1,343,837$
Sewer Capital Reserve 35 (56,900)$ -$
Sewer Plant Construction 52 -$ -$
Sewer Line Extension 46 -$ -$
Total 2,831,837$ 1,343,837$
*Cash/Investments/Net Accounts Receivable
Transfer in from Fund 26 & loan
proceeds to zero out fund
Doing in Fund 26 until Water
Upgrade Project closed out in
Rates TBD-Projected to increase
up to 9.7% for typical resident.
Funding from
Sugar/Teton/Developers with
Clawback TBD for Gravity Line
($2 M)
Will be exhausted by bond
payment/expansion projects
Transfer in from Fund 27 and 35
to zero out fund
Doing in Fund 27 until WW Plant
Final Phase Project closed out
Transfer to street
repair fund at
Yearend
Mostly URA
Receivable 2nd W
and 1st N-Should
get another
paydown in FY18
and be paid back if
land sells
Rates TBD-Projected to increase
5.6% or more for typical resident
Will have to decide what to pay
on DEQ Loan once finalized
Large Drop from the purchase of
3 garbage trucks in 2018-2019