Permit Status of (Issue) as of Report Date: 04/24/2018 9:37 am
Permit Details Permit Number: 13-00024
McDonald's
850 University Blvd
Building - Commercial
Permit Issued Date: 07/02/2013
Permit Inspection Statistics
36Total Inspections Completed:
32Total Inspections Passed:
Inspection Pass Rate: 88.89%
Permit Inspection History *Refer to Individual Inspection Report for more Details
06/04/2013PassQuinton OwensFooting Inspection
06/06/2013PassQuinton OwensFoundation Inspection
Ufer installed - #5 bar tied to vertical and 2 additional horiz bars.Inspector Comments:
07/15/2013PassBret StoddardElectrical Rough-in
Inspected three days on one ticket. 7/15-Approved to insulate the west wall from
the entry to back wall(north), 7/16-Approved for cover exterior walls on south
portion and bathrooms, 7/17-Verified ufer connection for electrical service.
Inspector Comments:
07/15/2013PassQuinton OwensSheeting
7/8,QO:Roof sheeting/parapet framing approved.
7/15,QO:Exterior wall- hold downs and anchor bolts good. Renail a few missed
locations as indicated.
Inspector Comments:
07/23/2013PassBret StoddardElectrical Rough-in
08/06/2013PassBret StoddardElectrical Service Inspection
Approved to be energized for permanent power.Inspector Comments:
Light pole footings (sauna tube) rebar looked good, pre-bent and tied
OK to Pout
Inspector Comments:
08/06/2013PassQuinton OwensFooting Inspection
8/6,QO: footing inspection for trash enclosure approved. Masonry wall sets right
on footing. Rebar as per plans.
Inspector Comments:
08/12/2013N/AQuinton OwensRadon-Ground Inspection
8/14,QO:Grease duct welding inspection. All holes fixed at inspection. Ok to
wrap.
Inspector Comments:
08/23/2013PassQuinton OwensHVAC Rough-in
8/22,QO:Duct on left only has one layer. Duct cleanouts covered on west duct
(2ea)
8/23: Duct wrap completed.
Inspector Comments:
08/23/2013PassQuinton OwensSuspending Ceiling Inspection
No area over 1,000 sf requires no additional seismic bracing. Normal installation
approved.
Inspector Comments:
Page 1 of 3
(Continued)
Permit Details Permit Number: 13-00024
McDonald's
850 University Blvd
Building - Commercial
Permit Status of (Issue) as of Report Date: 04/24/2018 9:37 am
Permit
Inspection
Summary
08/27/2013PassBret StoddardElectrical Rough-in
Approved for cover in the ceilings in the kitchen area only by the main cooking
equipment.
Inspector Comments:
08/29/2013PassBret StoddardElectrical Rough-in
Approved to install ceiling tiles in lobby-boxes in ceiling are being made up.Inspector Comments:
08/30/2013PassBret StoddardFire Alarm Final Inspection
Approved as a preliminary inspection final-Dale witnessed flow, 39 seconds, 24
hour/5 minute inspection not done.
Inspector Comments:
09/04/2013PassDon AllenPlumbing Sewer
09/04/2013PassDon AllenPlumbing Water
09/05/2013PassDale PickeringFire Underground Inspection
Underground flush and flow test for 10 minutes. Pito reading was 20psi on 2
1/2" line. Pass. DP
Inspector Comments:
09/05/2013PassQuinton OwensBuilding Final
09/05/2013FailQuinton OwensHVAC Final Inspection
Gas pressure regulator to vent outside or reinstall in horizontal upright position.
(per label)
Inspector Comments:
09/05/2013PassBret StoddardElectrical Final Inspection
Approved for a temporary final and C.O.-trash compound not done, signs and
wiring on roof and for menus not done. Call for a re-inspect when done for a
complete final.
Inspector Comments:
09/06/2013PassBret StoddardFire Alarm Final Inspection
Approved for a final and C.O.-fire alarm only, witnessed fan shut down and
monitoring for two large roof top units, flow switch and tamper switch operation
witnessed (8/30), 24 hour/ 5 minute test at 9:21AM 9/3 and AC power restored
at 9:50AM on 9/4. Report in file.
Inspector Comments:
09/10/2013PassQuinton OwensHVAC Final Inspection
gas regulator was reinstalled in horizontal, upright position.Inspector Comments:
09/11/2013PassDon AllenPlumbing Underground Inspection
All good to cover the under groundInspector Comments:
09/11/2013PassDon AllenPlumbing Rough-in
All good to cover the rough inInspector Comments:
09/18/2013PassDon AllenHVAC Rough-in
09/23/2013PassDale PickeringFire Sprinkler Rough-in
09/25/2013PassTed DyeFraming/Structure Inspection
OK to hang drywallInspector Comments:
09/25/2013PassTed DyeInsulation Inspection
Page 2 of 3
(Continued)
Permit Details Permit Number: 13-00024
McDonald's
850 University Blvd
Building - Commercial
Permit Status of (Issue) as of Report Date: 04/24/2018 9:37 am
Permit
Inspection
Summary
09/25/2013PassTed DyeSheetrock/Drywall Inspection
10/03/2013PassDon AllenPlumbing Final Inspection
10/04/2013FailJoel GrayPublic Works Final Inspection
10/07/2013PassNatalie PowellPlanning and Zoning Final Inspection
12/19/2013PassJohn MillarPublic Works Final Inspection
12/19/2013PassDale PickeringFire Sprinkler Final Inspection
12/23/2013PassBret StoddardElectrical Final Inspection
Approved for a final and C.O.-trash enclosure building completed.Inspector Comments:
03/09/2016PassJoel GraySidewalk Inspection
Page 3 of 3