HomeMy WebLinkAboutINSPECTION SUMMARY - 13-00093 - 1103 Greenside Loop - SFRPermit
Inspection
Summary
Permit Status of (Open) as of Report Date: 04/12/2018 8:20 am
Permit Details Permit Number: 13-00093
Single Family Residential
1103 Greenside Loop
Building - Single Family Residence
Permit Issued Date: 04/04/2013
Permit Inspection Statistics
19Total Inspections Completed:
13Total Inspections Passed:
Inspection Pass Rate: 68.42%
Permit Inspection History *Refer to Individual Inspection Report for more Details
04/01/2013PassQuinton OwensFoundation Inspection
Not ready as scheduled. Reinspect after noon - Rebar installed per city ordinance.Inspector Comments:
04/05/2013PassTed DyeFooting Inspection
Over laps of rebar good
rebar held off of ground
rebar clean
OK to pour
Inspector Comments:
04/09/2013PassDon AllenPlumbing Underground Inspection
all good to cover the ground workInspector Comments:
05/28/2013PassBret StoddardElectrical Service Inspection
Approved to be energized for permanent power-Fall River electric is
utility-provider.
Inspector Comments:
06/10/2013N/ATed DyeRadon-Ground Inspection
06/24/2013PassBret StoddardElectrical Rough-in
Approved for cover-unfinished basement entirely except the bathroom area (for a
hot tub).
Inspector Comments:
07/01/2013PassDon AllenPlumbing Rough-in
All good to cover the rough inInspector Comments:
07/01/2013PassDon AllenHVAC Rough-in
All good to cover the rough in Gas presser held at 20#Inspector Comments:
07/08/2013FailTed DyeFraming/Structure Inspection
Sheeting approved on walls Roofing sheeting was partialy done OK
Framing inspection disapproved:
Items are-
-Add studs under girder in NW bedroom.
-Get approval from truss company where additional rafters are added in front
room.
-have plans and truss details on site
-TJI top cord cut.repair as per TJI experts recommendation. Proved paper work.2
locations in basement in S.East bedroom.
Inspector Comments:
07/08/2013FailTed DyeFraming/Structure Inspection
Page 1 of 2
(Continued)
Permit Details Permit Number: 13-00093
Single Family Residential
1103 Greenside Loop
Building - Single Family Residence
Permit Status of (Open) as of Report Date: 04/12/2018 8:20 am
Permit
Inspection
Summary
07/15/2013PassBret StoddardSheetrock/Drywall Inspection
Approved to begin taping-5/8" type X throughout, garage not sheetrocked other
than the common wall with the house.
Inspector Comments:
07/16/2013PassTed DyeInsulation Inspection
02/05/2014PassBret StoddardCOM, COM-A, COM-R, and COM-T Electrical Final Inspection
Approved for a final and C.O.-unfinished basement except bathroom where toilet
and shower are installed-finished, no A/C unit installed.
Inspector Comments:
02/07/2014FailDon AllenPlumbing Final Inspection
need to trim out the main bath tub
install the trim on the shower down stairs
Inspector Comments:
all good for c\oInspector Comments:
02/25/2014PassDon AllenPlumbing Final Inspection
all good for c\oInspector Comments:
02/26/2014N/ATed DyeSidewalk Inspection
03/09/2016PassDon AllenHVAC Final Inspection
Building Inspection Type
02/25/2014PassTed DyeBuilding Final
2/5/14 - Final - trim out access (to attic) hole
Handrail needed on garage steps & landing.
CO smote detector need outside bedrooms.
Handrail needed on back patio.
1" Clearance around "B" vent.
Deck off mail level not complete.
Door disables keep until deck complete.
Action required: 20 AMP break.
Breaker lcok on oven circuit.
Inspector Comments:
Page 2 of 2