HomeMy WebLinkAboutChg Ord 1 - Well 9 ProposalAttachment 1 Proposed Unit Prices for Well #9 Change Order 1
Item No.Item Description Unit Bid
Quantity
Unit Bid
Price Bid Amount
SP-1
Provide all Mobilization,
Staging, Bonds, Insurance,
Demobilization, Other
Incidentals, and Cleanup
Necessary to Perform the
Work
LS 1 $3,000.00 $3,000.00
SP-2 Provide 22-Inch Drive Shoe EA 1 $600.00 $600.00
SP-3 Complete 22-inch Well
Drilling LF 60 $220.00 $13,200.00
SP-4 Provide and Install 22-inch
Surface Casing LF 60 $64.00 $3,840.00
SP-5 Pull 22-Inch Temporary
Surface Casing LF 60 $26.00 $1,560.00
SP-6 Provide 18-Inch Drive Shoe EA 1 $1,580.00 $1,580.00
SP-7 Complete 18-Inch Well
Drilling LF 260 $220.00 $57,200.00
SP-8 Provide and Install 18-Inch
Well Casing LF 232 $109.00 $25,288.00
SP-9 Provide 16-Inch Drive Shoe EA 0 $1,343.00 $0.00
SP-10 Complete 16-Inch Well
Drilling LF 0 $220.00 $0.00
SP-11 Provide and Install 16-Inch
Well Casing LF 0 $67.00 $0.00
SP-12 Install Cement Grout Surface
Seal CY 5 $190.00 $950.00
SP-13 Well Development HR 4 $200.00 $800.00
SP-14 Well Disinfection LS 1 $400.00 $400.00
SP-15 Mobilize and Set Test Pump LS 1 $5,600.00 $5,600.00
SP-16 Perform Pump Test HR 30 $350.00 $10,500.00
SP-17 Rig Time HR 4 $100.00 $400.00
SP-18
Provide and Install Pipe
Between City-Provided Trash
Pump and Irrigation Ditch
LF 600 $8.00 $4,800.00
TOTAL 129,718.00$
Well 9