CHANGE ORDER
No. 1
DATE OF ISSUANCE 4/3/2018 EFFECTIVE DATE 4/3/2018
OWNER City of Rexburg
CONTRACTOR High Plains Drilling
Contract: Production Well #8
Project: Production Well #8
OWNER's Contract No. WTR-01-18 ENGINEER's Contract No. _______________________
ENGINEER City of Rexburg
You are directed to make the following changes in the Contract Documents:
Description:
The Contractor agrees to construct Well #9 in accordance with the attached design. The contract
amount is increased by $129,718.00 in accordance with the attached proposal. The contract times
are increased by 30 days.
Reason for the Change:
The City previously received competitive bids for Well #8 on March 7, 2018 in accordance with
Idaho state requirements.
At the time of the bidding, the Well #9 plans were not yet complete; however, the design has since
been completed and the well has a similar design to Well #8.
The Contractor has agreed to honor the unit prices bid for Well #8, with just two exceptions. The
Contractor intends to reuse the Bid Item SP-2 22-Inch Drive Shoe which reduced the unit price of
that item and the unit price of SP-8 18-Inch Wall Casing was raised slightly due to fluctuating
steel prices.
Attachments: (List documents supporting change)
1. Proposed Unit Prices for Well #9
2. Well #9 Design
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price
$141,150.00
Original Contract Times:
Substantial Completion: 120 days
Ready for final payment: 120 days
(days or dates)
Net Increase (Decrease) from previous Change Orders
No. NA to NA:
$NA
Net change from previous Change Orders No. NA to
No. NA:
Substantial Completion: NA
Ready for final payment: NA
(days)
Contract Price prior to this Change Order:
$141,150.00
Contract Times prior to this Change Order:
Substantial Completion: 120 days
Ready for final payment: 120 days
(days or dates)
Net increase of this Change Order:
$129,718.00
Net increase this Change Order:
Substantial Completion: 30 days
Ready for final payment: 30 days
(days)
Page 2 of 2
Contract Price with all approved Change Orders:
$270,868.00
Contract Times with all approved Change Orders:
Substantial Completion: 150 days
Ready for final payment: 150 days
(days or dates)
APPROVED: ACCEPTED: By:___________________________ By: ______________________________ _ OWNER (Authorized Signature) CONTRACTOR (Authorized Signature) Date: _______________________ Date: _____________________________
APPROVED: By: ______________________________ FUNDING AGENCY (Authorized Signature) Date: ____________________________