HomeMy WebLinkAboutChg Ord 1 - Addition of Well 9Page 1 of 2 CHANGE ORDER No. 1 DATE OF ISSUANCE 4/3/2018 EFFECTIVE DATE 4/3/2018 OWNER City of Rexburg CONTRACTOR High Plains Drilling Contract: Production Well #8 Project: Production Well #8 OWNER's Contract No. WTR-01-18 ENGINEER's Contract No. _______________________ ENGINEER City of Rexburg You are directed to make the following changes in the Contract Documents: Description:  The Contractor agrees to construct Well #9 in accordance with the attached design. The contract amount is increased by $129,718.00 in accordance with the attached proposal. The contract times are increased by 30 days. Reason for the Change:  The City previously received competitive bids for Well #8 on March 7, 2018 in accordance with Idaho state requirements.  At the time of the bidding, the Well #9 plans were not yet complete; however, the design has since been completed and the well has a similar design to Well #8.  The Contractor has agreed to honor the unit prices bid for Well #8, with just two exceptions. The Contractor intends to reuse the Bid Item SP-2 22-Inch Drive Shoe which reduced the unit price of that item and the unit price of SP-8 18-Inch Wall Casing was raised slightly due to fluctuating steel prices. Attachments: (List documents supporting change) 1. Proposed Unit Prices for Well #9 2. Well #9 Design CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price $141,150.00 Original Contract Times: Substantial Completion: 120 days Ready for final payment: 120 days (days or dates) Net Increase (Decrease) from previous Change Orders No. NA to NA: $NA Net change from previous Change Orders No. NA to No. NA: Substantial Completion: NA Ready for final payment: NA (days) Contract Price prior to this Change Order: $141,150.00 Contract Times prior to this Change Order: Substantial Completion: 120 days Ready for final payment: 120 days (days or dates) Net increase of this Change Order: $129,718.00 Net increase this Change Order: Substantial Completion: 30 days Ready for final payment: 30 days (days) Page 2 of 2 Contract Price with all approved Change Orders: $270,868.00 Contract Times with all approved Change Orders: Substantial Completion: 150 days Ready for final payment: 150 days (days or dates) APPROVED: ACCEPTED: By:___________________________ By: ______________________________ _ OWNER (Authorized Signature) CONTRACTOR (Authorized Signature) Date: _______________________ Date: _____________________________ APPROVED: By: ______________________________ FUNDING AGENCY (Authorized Signature) Date: ____________________________