HomeMy WebLinkAboutINSPECTION SUMMARY - 17-00695 - 66 E Main St - Progrexion - RemodelPermit
Inspection
Summary
Permit Status of (Issue) as of Report Date: 03/09/2018 11:12 am
Permit Details Permit Number: 17-00695
Progrexion - Remodel
66 E Main St
Commercial Tenant Finish
Permit Issued Date: 11/28/2017
Permit Inspection Statistics
19Total Inspections Completed:
10Total Inspections Passed:
Inspection Pass Rate
52.63%
Permit Inspection History *Refer to Individual Inspection Report for more Details
01/17/2018N/AJoel GrayPublic Works Final Inspection
Interior tenant finish only.Inspector Comments:
Building Inspection Type
12/05/2017PARTPASSTed DyeCommercial Framing/Structure Inspection
When the remainder of the wall,electrical and plumbing inspections have been
done call for another inspection.
Inspector Comments:
12/13/2017PassQuinton OwensCommercial Sheetrock/Drywall Inspection
* Main floor drywall approved for taping (12/8)
* Basement level drywall approved for taping (12/11)
Inspector Comments:
01/12/2018FailQuinton OwensCommercial Building Final
01/16/2018FailQuinton OwensCommercial Building Final
Approved for temporary occupancy. Correct items as noted on HVAC, Building,
and Fire Department final inspections.
Inspector Comments:
02/13/2018PassQuinton OwensCommercial Building Final
Electrical Inspection Type
12/06/2017PassBret StoddardCommercial Electrical Rough-in
01/12/2018PassBret StoddardCommerical Electrical Final Inspection
Fire Inspection Type
01/12/2018FailBret StoddardFire Alarm Final Inspection
01/16/2018PassBret StoddardFire Alarm Final Inspection
01/16/2018FailDavid DavisFire Department Final Inspection
02/20/2018PassDale PickeringFire Department Final Inspection
Page 1 of 2
(Continued)
Permit Details Permit Number: 17-00695
Progrexion - Remodel
66 E Main St
Commercial Tenant Finish
Permit Status of (Issue) as of Report Date: 03/09/2018 11:12 am
Permit
Inspection
Summary
Mechanical Inspection Type
01/12/2018PARTPASSDon AllenHVAC Rough-in
Good for a temp.C/O. Will ned to see the exhaust boots installed and the duct
sealed.
Inspector Comments:
01/12/2018PARTPASSDon AllenHVAC Final Inspection
Good for a temp.C/O. Will ned to see the exhaust boots installed and the duct
sealed.
Inspector Comments:
01/16/2018PARTPASSQuinton OwensHVAC Final Inspection
Supply boots installed on duct, but duct is not sealed as noted on previous
inspection by Don.
* Approved only for temporary C.O.
Inspector Comments:
02/13/2018PassQuinton OwensHVAC Final Inspection
Ducts are sealed as needed. Joints exposed to conditioned rooms approved
without requiring sealing since any leakage will supply the room same as vents.
Inspector Comments:
Plumbing Inspection Type
12/05/2017PassDon AllenPlumbing Underground Inspection
Good to cover the plumbing underground. Before the final the back flows will
need to be inspected and tested.
Inspector Comments:
12/14/2017PassDon AllenPlumbing Rough-in
Good to cover the plumbing rough inInspector Comments:
01/12/2018PassDon AllenPlumbing Final Inspection
Good for the C/oInspector Comments:
Page 2 of 2