HomeMy WebLinkAboutINSPECTION TICKET - 17-00495 - 117 Madison - Replace Ele ServiceInspection
Ticket
Residential Electrical Service Inspection on 08/16/2017: PASS
Permit Number: 17-00495Permit Details
Electrical Only Residential
Permit Issued Date: 08/16/2017
Final Inspections Required
117 Madison
117 Madison - Replace Ele Service
Inspection Details
bret.stoddard@rexburg.org
Inspected By: Bret Stoddard
Residential Electrical Service Inspection on 08/16/2017: PASS
D ESCRIPTIO N CO MMEN TS STATUS
Overhead service conductors have proper
clearances. 230.24(A)&(B)
COMPLETED
Service disconnects and overcurrent devices
are located outside or inside nearest the point of
entrance of the service conductors. 230.70(A)
(1), 230.91
COMPLETED
Service disconnects are grouped together,
with no more than six in any one location.
230.71, 230.72, 408.36(B) Exc.
COMPLETED
The point of attachment is adequate and will
provide required support and clearances above
roofs
and grade. 230.24, 230.26, 230.54(C)
COMPLETED
Panelboards are grounded by an appropriate
and properly sized equipment grounding
conductor (or
conductors). 408.40, 215.6, 250.118, 250.122
COMPLETED
Unused openings have been effectively closed
(K.O. seals, etc.) 110.12(A), 408.7
COMPLETED
Securely mounted gear-panels, meter base, etc.
110.13
COMPLETED
Temperature ratings of equipment-lugs,
breakers, splices, etc. 110.14(A), (B), (C)
COMPLETED
Proper clearances about electrical equipment
indoors and outdoors. 110.26 (A), (E),(E)(2) and
(F)
COMPLETED
Grounding electrode system installed-ufer,
ground rods, metal water piping, etc. 250.52(A)
(4-7)
Grounding electrode system is existing.COMPLETED
Proper wiring bending space in panel &
associated enclosures, gutters, etc. 408.3(G),
312.6, 408.55(A)(B)&(C)
COMPLETED
Panel or switchgear service rated. 408.3(C)COMPLETED
Page 1 of 2
(Continued)
Permit Number: 17-00495
D ESCRIPTIO N CO MMEN TS STATUS
Main bonding jumper sized to 250.28(D), and all
panels bonded together using an equipment
bonding conductor sized in accordance with
250.122 or 250.66 as appropriate.
Bonding jumper is moved to the exterior panel
from the existing panel in the garage-(used to
be main panel).
COMPLETED
Service conductors are adequate size and rating.
230.23, 230.31, 230.42
COMPLETED
Approved to be energized for permanent power
(will send permit to utility).
To be re-energized for permanent
power-changed from a single meter to a double
meter pack.
COMPLETED