HomeMy WebLinkAboutINSPECTION SUMMARY - 16-00662 - Gravity FactoryPermit
Inspection
Summary
Permit Status of (Open) as of Report Date: 07/07/2017 9:30 am
Permit Details Permit Number: 16-00662
Gravity Factory
165 Airport Road
Building - Commercial
Permit Issued Date: 02/10/2017
Permit Inspection Statistics
48Total Inspections Completed:
29Total Inspections Passed:
Inspection Pass Rate
60.42%
Permit Inspection History *Refer to Individual Inspection Report for more Details
05/23/2017PassQuinton OwensPlanning and Zoning Final Inspection
06/08/2017PassJoel GrayPublic Works Final Inspection
Building Inspection Type
10/31/2016FailTed DyeCommercial Footing Inspection
Inspected East, South and West footings.
Remainder of footing to be called in for inspection on Tuesday.
Inspector Comments:
11/01/2016PassTed DyeCommercial Footing Inspection
11/03/2016PassTed DyeFoundation Inspection
260' of foundation wall. There is 95' on the south wall,
all of the East wall and 9' on the north wall foundations.
Inspector Comments:
11/04/2016PassQuinton OwensFoundation Inspection
PARTIAL FOUNDATION:
West half of south foundation and west wall except northwest corner. Piers and
grade beam on west wall are also not included.
Inspector Comments:
11/07/2016PassTed DyeFoundation Inspection
Remainder of North foundationInspector Comments:
11/08/2016FailQuinton OwensFoundation Inspection
Piers on west wall (grade beams on north and south ends not ready at this time).
Anchor rods not in yet for inspection. Rebar is as per plans.
Inspector Comments:
11/09/2016FailQuinton OwensFoundation Inspection
Piers on west wall only. Rebar installed as required. No anchor rods installed yet.
and grade beams on north and south end are not ready with rebar.
Inspector Comments:
11/10/2016PARTPASSQuinton OwensFoundation Inspection
West wall piers only. Grade beams at corners are not ready at this time.Inspector Comments:
11/14/2016FailQuinton OwensCommercial Footing Inspection
No footings to pour. Interior footings poured Friday without inspection (city
offices closed for Veteran's Day). Rebar identification required before covering
interior footings.
Inspector Comments:
Front outer entry vestibule framing only.
Sheeting approved to cover
Inspector Comments:
Page 1 of 4
(Continued)
Permit Details Permit Number: 16-00662
Gravity Factory
165 Airport Road
Building - Commercial
Permit Status of (Open) as of Report Date: 07/07/2017 9:30 am
Permit
Inspection
Summary
02/21/2017PARTPASSQuinton OwensSheeting
Note: Add missing screws to hold downs inside.
Inspector Comments:
Main open area of building insulated and covered without inspection.
Inspector Comments:
03/17/2017FailQuinton OwensCommercial Insulation Inspection
Fireblocking needed in mezzanine deck penetrations (fire rated at penetrations
above fire riser room).
Inspector Comments:
Screws added to hold downs in vestibule as required from previous inspection
(approved)
Inspector Comments:
Grab bar reinforcement is missing on ground floor restrooms.Inspector Comments:
03/17/2017FailQuinton OwensCommercial Framing/Structure Inspection
Missing stud on wall by fire riser. Reminder: Fire riser room is separated from the
rest of building with 1 hour minimum fire rating (walls are fire rated up to rated
deck above). Openings and penetrations must maintain fire rating.
Inspector Comments:
Re-inspection of front area exterior walls above & below mezzanine.Inspector Comments:
seal mezzanine floor penetrations. Openings above fire riser room shall be fire
rated and re-inspected (do not cover).
Inspector Comments:
03/21/2017PassQuinton OwensCommercial Insulation Inspection
Insulation approved for cover. Rough inspections not all completed above
mezzanine (approval required)
Inspector Comments:
03/21/2017PARTPASSQuinton OwensCommercial Framing/Structure Inspection
Main level framing is approved for cover. Not all rough-in work is done on upper
level. Framing re-inspection is needed above mezzanine after rough-in's are done
and for stair installation.
Inspector Comments:
Approved to tape other locations on main level. Upper floor is not ready (fire
rated penetration above riser room is approved for drywall cover).
Inspector Comments:
04/12/2017FailQuinton OwensCommercial Sheetrock/Drywall Inspection
Other areas not noted for corrections are approved for taping.
Inspector Comments:
04/17/2017PARTPASSQuinton OwensCommercial Sheetrock/Drywall Inspection
Re-inspection of main level & initial inspection of mezzanine level.Inspector Comments:
04/27/2017FailQuinton OwensCommercial Sheetrock/Drywall Inspection
No re-inspection called in for mezzanine level drywall or fire rating of riser room.
Follow-up call and inspection on 4/27 was after walls were painted.
Inspector Comments:
05/04/2017PassQuinton OwensSheeting
Floor sheeting for raised platforms. Missing nails added during inspection.Inspector Comments:
05/19/2017PassQuinton OwensCommercial Sheetrock/Drywall Inspection
Page 2 of 4
(Continued)
Permit Details Permit Number: 16-00662
Gravity Factory
165 Airport Road
Building - Commercial
Permit Status of (Open) as of Report Date: 07/07/2017 9:30 am
Permit
Inspection
Summary
05/19/2017PassQuinton OwensSuspending Ceiling Inspection
05/19/2017FailQuinton OwensCommercial Building Final
Re-inspection scheduled for late Monday morning.Inspector Comments:
05/22/2017FailQuinton OwensCommercial Building Final
Building final approved for temporary occupancy pending other final approvals
which have not been verified.
Inspector Comments:
06/29/2017PassQuinton OwensSidewalk Inspection
Approved for C.O. per conversation with Joel.Inspector Comments:
06/29/2017PassQuinton OwensCommercial Building Final
Approved for C.O.Inspector Comments:
Electrical Inspection Type
02/10/2017PassBret StoddardCOM & MFR Electrical Service Inspection
03/17/2017PARTPASSBret StoddardCommercial Electrical Rough-in
03/22/2017PARTPASSBret StoddardCommercial Electrical Rough-in
03/30/2017PassBret StoddardCommercial Electrical Rough-in
05/17/2017FailBret StoddardCommerical Electrical Final Inspection
05/18/2017PassBret StoddardCommerical Electrical Final Inspection
Fire Inspection Type
04/06/2017PassDale PickeringFire Sprinkler Rough-in
04/06/2017PassDale PickeringFire Sprinkler Hydro
05/17/2017PassDale PickeringFire Sprinkler Hydro
05/18/2017PassBret StoddardFire Alarm Final Inspection
05/24/2017PassDale PickeringFire Department Final Inspection
06/05/2017PassDale PickeringFire Department Final Inspection
06/26/2017PassDale PickeringFire Sprinkler Final Inspection
06/26/2017PassDale PickeringFire Department Final Inspection
Page 3 of 4
(Continued)
Permit Details Permit Number: 16-00662
Gravity Factory
165 Airport Road
Building - Commercial
Permit Status of (Open) as of Report Date: 07/07/2017 9:30 am
Permit
Inspection
Summary
Mechanical Inspection Type
03/20/2017FailDon AllenHVAC Rough-in
Need to finish rough in.Inspector Comments:
03/20/2017FailDon AllenGas Pressure Test
03/23/2017PassDon AllenHVAC Rough-in
03/23/2017PassDon AllenGas Pressure Test
05/19/2017PassDon AllenHVAC Final Inspection
Good for the C/OInspector Comments:
Plumbing Inspection Type
11/16/2016PassDon AllenPlumbing Underground Inspection
Good to cover the plumbing undergroundInspector Comments:
05/19/2017PassDon AllenPlumbing Final Inspection
06/08/2017PassDon AllenPlumbing Water
06/08/2017PassDon AllenPlumbing Sewer
Page 4 of 4